The Ministry of Industry and Trade promulgates Circular 10/2017/TT-BCT on the technical safety inspection procedures for machinery, equipment, and materials with strict safety requirements.
According to the inspection procedures issued in Circular 10, the following conditions must be met when conducting boiler inspections:
- The boiler must be in a state ready for inspection.- The boiler's documentation and records must be complete.- Environmental and weather factors should not affect the inspection results.- Safety, occupational hygiene, and fire prevention conditions must be met for boiler inspection.
The boiler inspection will be carried out in 06 steps as follows:
- Preparation work before conducting the inspection.- Checking boiler documentation and history.- External and internal technical inspection.- Hydraulic testing.- Operational inspection.- Processing inspection results.
Note: The following inspection steps should only proceed if the preceding step's results meet the required standards.
See more inspection forms in Circular 10/2017/TT-BCT, effective from September 15, 2017.