Circular 10/2023/TT-BCT amend Circular 21/2020/TT-BCT stipulating the order and procedures for granting electricity activity licenses, in which amending application for licenses in the field of electricity transmission and distribution.
Application for issuance of license in the field of electricity transmission and distribution in Vietnam is as follows:
- The application form for electricity license made using the Form No. 01 provided in the Appendix enclosed with Circular 21/2020/TT-BCT.
- The copy of the applicant’s enterprise registration certificate, establishment decision or certificate of incorporation (in case of unavailability of the enterprise registration certificate).
- The list of technical managers and shift leaders of the power plant made according to Form No. 3b in the Appendix enclosed with Circular 21/2020/TT-BCT;
Copies of their academic qualifications and employment contracts; (compared to the current one, a copy of theeployment contract is added)
Documents proving working experience in electricity transmission and distribution of technical managers (curriculum vitae certified by the employers or other documents of equivalent validity); (additional content)
Certificates of completion of safety training courses or electrical safety cards as prescribed in Article 64 of the Law on Electricity, and operation certificates issued to the listed shift leaders by competent power load dispatch units according to the National load dispatch procedures adopted by the Ministry of Industry and Trade
- The list of electrical grid works (technology equipment, lines and substations) managed by the applicant and scopes thereof.
The copy of the acceptance test report on completion of installation of electrical grid works (technology equipment, lines and substations).
In case of purchase, acquisition or transfer of the electrical grid, the acceptance test report on the grid works or the asset transfer record is required.
In case of the electrical grid under common ownership by multiple investors, the agreement or the letter of authorization from the investors to an operating unit is required
- A copy of the Agreement on connection to the national electricity system as prescribed; grid boundary map and operating range.
Circular 10/2023/TT-BCT takes effect from June 9, 2023.
Address: | 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City |
Phone: | (028) 7302 2286 |
E-mail: | info@lawnet.vn |