Vietnam: Dossier for addition of project in the biomass energy use and development planning

On September 09, 2015, the Ministry of Industry and Trade of Vietnam issued Circular No. 44/2015/TT-BCT providing for the project development, the avoidable cost tariff and the sample of electricity sale Contract applicable to biomass power projects.

According to Article 4 of Circular No. 44/2015/TT-BCT of the Ministry of Industry and Trade of Vietnam, the dossier for addition of project in the biomass energy use and development planning includes:

Hồ sơ đề nghị bổ sung dự án vào quy hoạch năng lượng sinh khối, 44/2015/TT-BCT

- The report of the Chairman of People’s Committee at provincial level to request the addition of project in the biomass energy use and development planning.

- Basic information about the investor: Documents of legal status, business registration, key personnel, experience in project implementation, financial and technical capacity particularly the list of completed projects must be declared (including electricity and engineering projects, if any).

- Information about the proposed biomass power project

+ Type of biomass and supply capacity;

+ The necessity for investment in project development, favorable and difficult conditions, regulation on exploitation and use of national natural resources (if any);

+ Project description: location, scale and area of works construction, works items of project; contents of sector planning and construction planning of locality;

+ Brief presentation of implementation solutions: The technical and technological plan and capacity; technical infrastructure connection plan; equipment installation plan; implementation progress and form of project management; general plan about relocation compensation and technical infrastructure building assistance plan (if any) and cost plan;

+ Assessment of environmental impact, solutions to fire prevention and fighting and requirements for security and national defense;

+ Total investment of project; capital arrangement capability, capital and financing capability based on the progress; analysis and assessment of economic, financial and social effects of projects.

- Opinions of the regional Power Corporation or power transmission unit (if connected to the transmission power system) about the Dossier for planning addition.

View details at Circular No. 44/2015/TT-BCT of the Ministry of Industry and Trade of Vietnam, effective from January 25, 2016.

Thu Ba

>> CLICK HERE TO READ THIS ARTICLE IN VIETNAMESE

21 lượt xem



Related Document
  • Address: 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City
    Phone: (028) 7302 2286
    E-mail: info@lawnet.vn
Parent company: THU VIEN PHAP LUAT Ltd.
Editorial Director: Mr. Bui Tuong Vu - Tel. 028 3935 2079
P.702A , Centre Point, 106 Nguyen Van Troi, Ward 8, Phu Nhuan District, HCM City;