On January 18, 2016, the Ministry of Finance of Vietnam issued Circular 09/2016/TT-BTC stipulating the finalization of completed projects funded by state capital. Following forms are attached to the Circular:
No | Form | Content |
|
Form No: 01/QTDA | Consolidated report on project completion settlement |
|
Form No: 02/QTDA | List of legal documents and construction contracts |
|
Form No: 03/QTDA | Comparison table of capital allocation, lending, and investment capital payment figures |
|
Form No: 04/QTDA | Investment costs proposed for settlement |
|
Form No: 05/QTDA | Newly increased long-term (fixed) assets |
|
Form No: 06/QTDA | Short-term assets handed over |
|
Form No: 07/QTDA | Status of project payments and debts |
|
Form No: 08/QTDA | Report on completed investment capital settlement |
|
Form No: 09/QTDA | Report on the results of settlement approval for national important projects/group A projects/program projects |
|
Form No: 10/QTDA | Decision on the approval of project completion settlement |
|
Form No: 11/QTDA | Consolidated report on project completion settlement |
|
Form No: 12/QTDA | Consolidated report on project completion settlement |
|
Form No: 13/QTDA | Receipt note |
|
Form No: 14/QTDA | Supplemental document* to complete*, project settlement dossier (items, bidding packages)... |
Detailed forms can be found in Circular 09/2016/TT-BTC effective from March 5, 2016 in Vietnam.