Documents for assessment and approval of contractor selection results to sign petroleum contracts in Vietnam

Pursuant to Clause 1, Article 20 of Decree 45/2023/ND-CP, documents for assessment and approval of contractor selection results to sign petroleum contracts consist of:

- Presentation of bid evaluation results and proposed contractors to sign petroleum contracts together with economic and technical conditions of petroleum contracts;

- Bidding documents or shopping documents or request for proposals;

- Bids, competitive bidding documents, or request for proposals;

- Record of bid opening;

- Record of contractor assessment, scoring sheets;

- Documents of PVN requesting clarification to bids or shopping documents or request for proposals and written response of bidders (if any);

- Other relevant documents.

Documents for assessment and approval of contractor selection results to sign petroleum contracts in Vietnam

Documents for assessment and approval of contractor selection results to sign petroleum contracts in Vietnam (Internet image) 

Content of assessment of contractor selection results to sign petroleum contracts in Vietnam

Pursuant to Clause 2, Article 20 of Decree 45/2023/ND-CP, assessment of contractor selection results to sign petroleum contracts includes:

- Assessment of the basis of contractor selection process;

- Assessment of compliance with time regulations during contractor selection process;

- Assessment of appropriateness of assessment solutions and contractor selection criteria;

- Assessment of compliance with the law during evaluation of bids, competitive bidding documents, and request for proposals;

- Consideration of different opinions (if any) of expert teams;

- Other relevant details.

Procedures for assessment and approval of contractor selection results to sign petroleum contracts in Vietnam

Pursuant to Article 20 of Decree 45/2023/ND-CP, the order and procedures for appraisal and approval of the results of selecting contractors to sign oil and gas contracts are as follows:

-  Within 15 days from the date on which contractor selection results are assessed, PVN shall submit 2 sets of documents (1 set of original documents and 1 set of copies) to the Ministry of Industry and Trade directly or via post service to request for approval of contractor selection results to sign petroleum contracts.

- Within 5 working days from the date on which adequate documents are received, the Ministry of Industry and Trade shall send written request to the Ministry of Planning and Investment, Ministry of Finance, Ministry of Justice, Ministry of National Defense, Ministry of Foreign Affairs, Ministry of Public Security, Committee for Management of State Capital at Enterprises (if PVN participates in petroleum contracts as contractors), and relevant ministries, central departments to provide feedback.

- Within 15 days from the date on which written request for feedback sent by the Ministry of Industry and Trade is received, ministries and central departments must send written feedback within their competence to the Ministry of Industry and Trade.

- Within 45 days from the date on which adequate documents are received, the Ministry of Industry and Trade shall assess contractor selection results to sign petroleum contracts and request the Prime Minister to consider and approve. The documents consist of:

= Written presentation of assessment results and written request for approval of contractor selection results to sign petroleum contract to be sent to the Prime Minister;

= Documents under Section 1

= Consolidated report on acknowledgement and presentation of feedback of ministries, central departments, and copies of written feedback of ministries and central departments.

- Within 15 days from the date on which written approval for contractor selection results sent by the Prime Minister is received, the PVN shall inform bidders about contractor selection results, basic economic and technical conditions of petroleum contracts, and plans for negotiating petroleum contracts.

- Within 90 days from the date on which notice on contractor selection results sent by the PVN is received, contractors and PVN must finish negotiating petroleum contracts. If details of draft petroleum contracts have not been agreed upon within the aforementioned time limit, the PVN shall file reasons for disagreement and proposed negotiation time limit to the Ministry of Industry and Trade.

Mai Thanh Loi

>> CLICK HERE TO READ THIS ARTICLE IN VIETNAMESE

110 lượt xem



Related Document
  • Address: 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City
    Phone: (028) 7302 2286
    E-mail: info@lawnet.vn
Parent company: THU VIEN PHAP LUAT Ltd.
Editorial Director: Mr. Bui Tuong Vu - Tel. 028 3935 2079
P.702A , Centre Point, 106 Nguyen Van Troi, Ward 8, Phu Nhuan District, HCM City;