The Ministry of Public Security issues Circular 59/2017/TT-BCA regulating the monitoring and evaluation of investment in the People's Public Security.
According to Circular 59, the monitoring and evaluation of the component project owner are stipulated as follows:
- The component project owner assigned to implement the component project shall organize the monitoring of the investment project, inspect the investment project, and evaluate the investment project;
- The monitoring of the component project under the program of the component project owner shall comply with the provisions of Clause 1, Article 8 of Decree 84/2015/ND-CP.
- The contents of the inspection and evaluation by the component project owner shall be carried out in the order stipulated in Articles 14 and 15 of Circular 59.
- Monitoring reports of the component project owner:
- The component project owner shall conduct monitoring and evaluation of the investment in the following types of reports:- Quarterly I report, 6-month report, quarterly III report, and annual report submitted to the program owner for summary reporting;- Monitoring and evaluation report upon completion of the investment in the component project submitted to the program owner for summary and monitoring.- Report deadlines:- Submit the quarterly report before the 5th of the first month of the following quarter;- Submit the 6-month report before July 5 of the reporting year;- Submit the annual report before February 5 of the following year;- The component project owner may provide ad-hoc reports on monitoring and evaluation of the investment when necessary and upon the request of the authority authorized to decide the investment and the Department of Planning and Investment.
See more Monitoring Report Form at Circular 59/2017/TT-BCA effective from January 23, 2018.
- Thanh Lam -