Circular 34/2018/TT-BCT has been issued by the Ministry of Industry and Trade stipulating the inspection and acceptance of the volume of overburden removal in open-pit coal mining.
According to Circular 34, the acceptance inspection schedule for excavated and transported earth and rock is stipulated as follows:
- Monthly, organizations and individuals engaged in extraction must conduct acceptance inspections of the excavated and transported earth and rock volumes. The acceptance inspection period for the previous month is from the 1st to the 10th of the subsequent month. The acceptance inspection data is calculated up to the last day of the month. In cases where the volume of excavated earth and rock at the mining site is ≤ 10,000 m3/month, acceptance inspection measurements are permitted to be conducted quarterly.- Quarterly, organizations and individuals engaged in integrated coal mining must conduct quarterly acceptance inspections. The compilation period for the previous quarter’s acceptance inspection volume is from the 1st to the 15th of the first month of the subsequent quarter.- Annually, organizations and individuals engaged in coal mining must conduct annual acceptance inspections. The compilation period for the annual acceptance inspection volume is from the 1st to the 15th of the first month of the following year.
Refer to the acceptance inspection documentation at Circular 34/2018/TT-BCT, which took effect on November 26, 2018.
- Thanh Lam -
Address: | 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City |
Phone: | (028) 7302 2286 |
E-mail: | info@lawnet.vn |