Which facilities and works are required to appraise of fire safety designs in Vietnam?

Please ask, which facilities and works are required to appraise of fire safety designs in Vietnam? Looking forward to hearing from you soon.

Facilities and works are required to appraise of fire safety designs in Vietnam specified in Appendix V of Decree 136/2020/ND-CP, specifically as follows:

1. Premises of regulatory bodies at all levels with at least 7 stories or total volume of at least 5.000 m3.

2. Apartment buildings, tenement houses and dormitories with at least 7 stories or total volume of at least 5.000 m3; mixed-use buildings with at least 7 stories or total volume of at least 5.000 m3.

3. Junior kindergartens and senior kindergartens with at least 100 students or total volume of at least 3.000 m3; primary schools, lower secondary schools, upper secondary schools and multi-level secondary schools with total volume of at least 5.000 m3; colleges, universities, academies; post-secondary schools; vocational schools; continuing education institutions; and other educational institutions established under the Education Law with at least 5 stories or total volume of at least 5.000 m3.

4. Hospitals; polyclinics, clinics, sanitariums, physical rehabilitation facilities, orthopedic facilities, nursing homes, epidemic prevention and control facilities, medical centers and other healthcare facilities established under the Law on Medical Examination and Treatment with at least 5 stories or total volume of at least 3.000 m3.

5. Theaters, cinemas and circuses with at least 300 seats; convention centers with at least 5 stories or total volume of at least 5.000 m3; cultural centers, karaoke facilities and night clubs with at least 3 stories or volume of at least 1.000 m3; bars, clubs, beauty clinics, massage shops, theme parks, zoos and aquariums with at least 3 stories or total volume of at least 1.500 m3.

6. Markets; shopping malls; supermarkets; department stores; convenience stores; restaurants and eateries with total volume of at least 3.000 m3.

7. Hotels, guest houses, rented houses and other types of lodgings established under the Law on Tourism with at least 7 stories or total volume of at least 5.000 m3.

8. Workplaces of enterprises and socio - political organizations with at least 7 stories or total volume of at least 5.000 m3.

9. Museums, libraries; exhibits; storage facilities, bookstores and fair facilities with total volume of at least 5.000 m3.

10. Post offices and broadcasting and telecommunications facilities; information equipment housing units and data storage and management centers with at least 5 stories or total volume of at least 5.000 m3.

11. Stadiums with at least 5.000 seats; arenas, sports centers racing tracks, shooting ranges and other sports facilities established under the Law on Physical Training and Sports with at least 5.000 seats or total volume of at least 5.000 m3.

12. Airports, air traffic control towers; wharves of seaports; dry ports; inland ports; coach stations; rail stations; aerial passenger tramway terminals and rest stops with total volume of at least 1.500 m3; subway facilities; motor vehicle registration facilities; and automobile, motorcycle and moped trading and maintenance facilities with business space of at least 500 m2 or volume of at least 5.000 m3.

13. Indoor garages with total volume of at least 3.000 m3.

14. Road tunnels of at least 500 m; railway tunnels of at least 1.000 m.

15. Nuclear facilities; facilities producing, trading and preserving industrial explosives and explosive precursors; industrial explosive and explosive precursor storage; industrial explosive and explosive precursor import and export ports; weapon and combat gear storage.

16. Facilities for extracting, processing, producing, transporting, trading and preserving petroleum, petroleum products and gas on land; petroleum and petroleum product terminals, gas terminals; petroleum, petroleum product and gas import and export ports; filling stations, internal filling stations with at least 01 fuel dispenser; gas stations and internal gas supply systems with total gas storage of at least 200 kg.

17. Industrial facilities with grade A or B risk of fire and explosion and total volume of at least 1.500 m3; and grade C, D or E risk of fire and explosion and total volume of at least 5.000 m3.

18. Power plants; electrical substations with voltage of at least 110 kV.

19. Tunnels with production, storage and use of flammable materials and explosives and total volume of at least 1.000 m3. Warehouses of flammable goods or non-flammable goods contained in flammable packaging with total volume of at least 3.000 m3.

20. Technical infrastructures related to fire prevention and fighting of cities, economic zones, industrial parks, industry clusters, export-processing zones, hi-tech parks and other functional zones according to the Law on Planning requiring approval from authority at district level or higher.

21. Motor vehicles subject to special requirements for fire safety. Railway vehicles and watercrafts at least 20 m in length transporting passengers, gasoline, oil, flammable liquids, flammable gas, explosives and chemicals posing fire and explosion hazards.

Best Regards!

Related Posts
LawNet
What are support levels for damage from natural disasters, plant pests in Vietnam from February 25, 2025?
LawNet
Decree 18/2025/ND-CP providing guidance on the Law on Electricity related to electricity trading activities and ensuring power supply situations in Vietnam
LawNet
What is the significance of January 8? Which areas are prohibited from mineral activities in Vietnam?
LawNet
What are environmental protection tax rates for gasoline, oil, and lubricants in Vietnam January 1, 2025?
LawNet
What is the electricity transmission price until December 31, 2024 in Vietnam?
LawNet
Circular 35/2024/TT-BTNMT on technical procedures for the collection, transportation, and treatment of domestic solid waste in Vietnam
LawNet
Promulgation of the Law on Electricity 2024 in Vietnam from February 1, 2025
LawNet
Promulgation of the Law on Geology and Minerals 2024 in Vietnam
LawNet
Promulgation of the Law on Fire Prevention and Fighting and Rescue in 2024 in Vietnam
LawNet
Three cases of suspension due to failure to ensure fire prevention and fighting in Vietnam
Lượt xem: 0
Latest Post

Đơn vị chủ quản: Công ty THƯ VIỆN PHÁP LUẬT.
Chịu trách nhiệm chính: Ông Bùi Tường Vũ - Số điện thoại liên hệ: 028 3935 2079
P.702A , Centre Point, 106 Nguyễn Văn Trỗi, P.8, Q. Phú Nhuận, TP. HCM;