What do construction quality documents in Vietnam include?
According to regulations on construction quality control and maintenance. What do construction quality documents in Vietnam include? I look forward to receiving your feedback.
What do construction quality documents in Vietnam include? (Image from the Internet)
Construction quality documents include dossiers specified in Appendix III of Circular 26/2016/TT-BXD regulating construction quality control and maintenance issued by the Ministry of Construction. To be specific:
- Revisions to the design during the construction and the competent authority’s written assessment or approval.
- As-built drawings ( enclosed with the list of as-built documents).
- Construction quality control plans and measures.
- Certificates of origins, product labels, written announcement of applicable standards; certificates and declaration of conformity and professional authority’s announcement of receipt of declaration of conformity under the Law on Goods quality.
- Results of monitoring, measurements and experiment in construction process and monitoring results in the process of operation .
- Records of acceptance of building tasks and partial acceptance (if any) during the construction.
- Results of control experiments, quality assessment and testing of the bearing capacity of the construction structure (if any).
- Briefs of installed equipment .
- Construction works’ operation and maintenance manuals.
- The State competent authority’s written agreement , approval or confirmation (if any) about:
+ Relocation of residents from reservoirs, survey of cultural and historical remains;
+ Fire safety;
+ Environmental protection;
+ Occupational safety and technology and equipment operation manual;
+ Construction permit (where it is required);
+ Permission to connect to infrastructures and other relevant construction works;
+ Other documents under regulations of laws.
- Construction incident records (if any).
- Records of acceptance of construction works and work items prior to operation.
- Annexes on shortcomings (if any) after the construction comes into operation.
- Other documents related to construction and acceptance of construction works.
- The construction authority’s written notifications of the results of acceptance inspection in the process of construction and written notification of approval for acceptance result of work item and construction works.