What are marine works in the construction work hierarchy in Vietnam?
What are marine works in the construction work hierarchy in Vietnam? What are aviation works in the construction work hierarchy in Vietnam? What are regulations on decentralization of works for agriculture and rural development (agriculture and rural development works in Vietnam?
Thank you!
What are marine works in the construction work hierarchy in Vietnam?
Pursuant to Section 1.4.5, Table 1.4, Appendix 1 issued together with the Circular 06/2021/TT-BXD stipulating as follows:
1.4.5 |
Marine works |
||||||
1.4.5.1 Seaport works; transshipment zone; anchorage area; storm shelter |
|||||||
a) Goods and public service ports |
Vessel tonnage (thousand DWT) |
> 70 |
> 40 ÷ 70 |
> 20 ÷ 40 |
> 5 ÷ 20 |
≤ 5
|
|
b) Passenger terminal |
Total tonnage of the ship (thousand GT) |
> 150 |
> 100 ÷ 150 |
> 50 ÷ 100 |
> 30 ÷ 50 |
≤ 30 |
|
c) Transshipment area; anchorage area; storm shelter |
Vessel tonnage (thousand DWT) |
> 70 |
> 40 ÷ 70 |
> 20 ÷ 40 |
> 5 ÷ 20 |
≤ 5
|
|
1.4.5.2 Ship and watercraft repair facilities; locks, docks and other ship-lifting works (riddles, ramps, raised platforms, etc) |
Vessel tonnage (thousand DWT) |
> 70 |
> 40 ÷ 70 |
> 20 ÷ 40 |
> 5 ÷ 20 |
≤ 5 |
|
1.4.5.3 Navigational Channels |
Width of one lane channel B (m) or Running depth Hct (m) |
B > 190 or Hct ≥ 16 |
140 < B ≤ 190 or 14 ≤ Hct < 16 |
80 < B ≤ 140 or 8 ≤ Hct < 14 |
50 < B ≤ 80 or 5 ≤ Hct < 8 |
B ≤ 50 or Hct < 5 |
|
1.4.5.4 Other marine works: |
|||||||
a) Marine signaling buoys |
Float diameter D (m) |
D ≥ 10 |
5 ≤ D < 10 |
3 ≤ D < 5 |
2 ≤ D < 3 |
D < 2 |
|
b) Correction works, breakwaters, sand-proof dikes, diversionary embankments, shore protection embankments |
Maximum height of building or water depth H (m) |
H > 16 |
12 < H ≤ 16 |
8< H ≤ 12 |
5≤ H 8 |
< 5 |
What are aviation works in the construction work hierarchy in Vietnam?
Pursuant to Section 1.4.6, Table 1.4, Appendix 1 issued together with the Circular 06/2021/TT-BXD stipulating as follows:
1.4.6 |
Aviation works |
||||||
1.4.6.1 Airport Terminal (Main Terminal) |
Number of passengers (million passengers/year) |
≥ 10 |
< 10 |
||||
1.4.6.2 Flight area |
Airport level according to regulations of the International Civil Aviation Organization (ICAO) |
Airports of level 4E or higher |
Airports less than level 4E |
||||
1.4.6.3 Works to ensure flight operations (Air Traffic Control Tower, Long Distance Control Center, Approach Control Center, Primary/Secondary Radar Station; excluding sections 1.4.6.2 and 1.4.6.4) |
Critical level |
International Airport |
International Airport, domestic airport |
||||
1.4.6.4 Airline carrier |
Critical level |
Level I of all sizes. |
Note:
- For other traffic works with the purpose of use suitable to the type of works mentioned in Table 1.4, they shall be used to determine the grade according to the importance or capacity scale.
- Refer to the examples of determining the grade of traffic works in Appendix III.
What are regulations on decentralization of works for agriculture and rural development (agriculture and rural development works in Vietnam?
Pursuant to Table 1.5, Appendix 1 issued together with the Circular 06/2021/TT-BXD stipulating as follows:
No. |
Type of construction |
Classification criteria |
Building level |
||||
Special |
Level I |
Level II |
Level III |
Level IV |
|||
1.5.1 |
Irrigation works |
||||||
1.5.1.1 Water supply (for irrigated area) or drainage (for natural area of drainage area) |
Area (thousand hectares) |
> 50 |
> 10 ÷ 50 |
> 2 ÷ 10 |
≤ 2 |
||
1.5.1.2 Reservoir corresponding to normal water level rise |
Capacity (million m3 ) |
> 1,000 |
> 200 ÷ 1.000 |
> 20 ÷ 200 |
≥ 3 ÷ 20 |
< 3 |
|
1.5.1.3 Works supplying untreated water to other water-using industries |
Flow (m3 /s) |
> 20 |
> 10 ÷ 20 |
> 2 ÷ 10 |
≤ 2
|
||
1.5.2 |
Dike works: Determine grade according to the decentralization decision of the Ministry of Agriculture and Rural Development authorized by the Government under Clause 2, Article 2 of Decree No. 113/2007/ND-CP dated June 28, 2007 of the Government detailing and guiding the implementation of a number of articles of the Law on Dykes. |
Note:
- Other agricultural and rural development (Agriculture and Rural Development) works with the purpose of use suitable to the type of works mentioned in Table 1.5, they shall be used to determine the grade by importance or capacity scale.
- For livestock production, cultivation, forestry, salt production, fisheries, new rural construction and other agriculture and rural development projects, due to the specificity, in investment projects to build these works often including types of works such as: civil works, industrial works, traffic works, irrigation works, technical infrastructure works, etc. When decentralizing works, it will depend on specific cases to apply decentralization accordingly on the basis of the principles of decentralization specified in this Circular.
- Refer to the examples of determining the level of agricultural and rural development works in Appendix III.