Pursuant to Clause 1 Article 19 of the Decree 06/2021/ND-CP stipulating following regulations:
Construction projects must be supervised during the construction period in accordance with Clause 1, Article 120 of Law No. 50/2014/QH13.
The construction supervision involves:
a) Checking the relevance of the construction contractor's capacity for that stated in the bidding documents and construction contracts, including: manpower, equipment, specialized laboratories, quality management systems of construction contractors;
b) Comparing the contractor's construction method with the approved construction method design. Approving the general safety plan and detailed safety assurance measures for specific works or those with high risks of occupational unsafety at construction sites;
c) Considering acceptance of the regulations laid down in Clause 3, Article 13 of this Decree submitted by the contractor and requesting the construction contractor to modify those during the construction process to adapt to the reality and contractual terms and conditions. Where necessary, investors shall agree in construction contracts with contractors on authorizing construction supervision contractors to formulate and request construction contractors to implement the above regulations.
d) Carrying out the inspection and grant approval of building materials, components, products and equipment for use in construction projects;
dd) Inspecting and pushing construction contractors and other contractors to carry out the construction works at construction sites as required by construction designs and construction schedules of the works;
e) Supervising the implementation of regulations on safety management of construction activities; supervising safety measures for adjacent construction works and observations at construction sites;
g) Requesting investors to adjust the detailed design whenever detecting any errors and irrationalities in that design;
h) Requesting contractors to temporarily suspend or terminate the construction works when realizing that the construction quality does not meet technical requirements; construction measures are unsafe; violations against regulations on management of occupational safety cause or pose risks of occupational accidents or incidents leading to occupational unsafety; presiding over, and cooperating with stakeholders in, settling problems arising in the process of construction and cooperating in handling and mitigating consequences of incidents in accordance with this Decree;
i) Examining and evaluating the results of test of construction materials, components and products during the construction process and other relevant documents necessary for the pre-commissioning test; verifying and confirming as-built drawings;
k) Conducting the controlled experiment and quality inspection of construction project constituents, items and construction works according to the provisions of Article 5 of this Decree (if any);
l) Carrying out pre-commissioning tests as prescribed in Articles 21, 22 and 23 of this Decree; inspecting and confirming the completed construction quantities;
m) Performing other tasks prescribed in construction contracts.