What are conditions for issuance of construction survey practicing certificates in 2024 in Vietnam?
What are conditions for issuance of construction survey practicing certificates in 2024 in Vietnam? Who shall establish the construction survey objectives in Vietnam?
What are conditions for issuance of construction survey practicing certificates in 2024 in Vietnam?
Pursuant to Article 68 of the Decree 15/2021/ND-CP stipulating conditions for issuance of construction survey practicing certificates:
- An individual may be issued with a construction survey practicing certificate if he/she meet the eligibility requirements in Articles 66 and 67 of the Decree 15/2021/ND-CP.
- An individual may be issued with a construction survey practicing certificate if he/she meet the eligibility requirements corresponding to the following ranks:
+ A Rank-I construction survey practicing certificate is awarded to the individual who has worked as a president in charge of construction survey in the field for which a practicing certificate is sought of at least 01 group A project or higher or 02 group B projects or higher or at least 01 Class I works or higher or at least 02 Class II works or higher.
+ A Rank-II construction survey practicing certificate is awarded to the individual who has worked as a president in charge of construction survey in the field for which a practicing certificate is sought of at least 01 group B project or higher or 02 group C projects or higher or at least 01 Class II works or higher or at least 02 Class III works or higher.
+ A Rank-III construction survey practicing certificate is awarded to the individual who has worked as a president in charge of construction survey in the field for which a practicing certificate is sought of at least 01 group C projects or higher or 02 projects that require economic - technical reports or at least 01 Class III works or higher or at least 02 Class IV works.
What are conditions for issuance of construction survey practicing certificates in 2024 in Vietnam? - image from internet
Who shall establish the construction survey objectives in Vietnam?
Pursuant to Clause 2 Article 26 of the Decree 15/2021/ND-CP stipulating the construction survey objectives in Vietnam:
Construction survey objectives
1. The plan on construction survey objectives is established for the survey activities, supporting the establishment of construction investment project, construction engineering plan, engineering plan on repair, renovation and expansion of works or supporting other survey activities relating to the construction.
2. The construction survey objectives shall be established by the designing contractor. In case the designing contractor has not been chosen or in other survey circumstances, the investment-decision maker or the investor or authority having competence to establish a PPP project may hire a qualified organization/individual to establish the plan on construction survey objectives.
3. The construction survey objectives shall be designated to the surveying contractor by the investor through the conclusion of an agreement on construction survey or designated to the designing contractor if the designing contractor performs both construction survey and construction design.
4. The plan on construction survey objectives shall include:
a) Targets of construction survey;
b) Scope of construction survey;
c) Requirements for application of technical regulations and standards on construction survey;
d) Estimate of activities for construction survey and cost estimate for construction survey activities (if any);
dd) Duration of construction survey.
...
As regulated above, the construction survey objectives shall be established by the designing contractor.
In case the designing contractor has not been chosen or in other survey circumstances, the investment-decision maker or the investor or authority having competence to establish a PPP project may hire a qualified organization/individual to establish the plan on construction survey objectives.
What are contents of construction survey report in Vietnam?
Pursuant to Article 29 of the Decree 15/2021/ND-CP stipulating contents of construction survey report in Vietnam:
Content of construction survey report
1. Basis for construction survey
2. Procedures and methods for construction survey.
3. The generality of location and natural conditions of the construction survey site, characteristics and scope of the construction.
4. Load of completed construction surveys.
5. Experimented and analyzed result and data from construction survey.
6. The opinions, notes and/or suggestions (if any).
7. Conclusions and proposed solutions.
8. Appendixes.
As regulated above, construction survey report in Vietnam includes following contents:
- Basis for construction survey
- Procedures and methods for construction survey.
- The generality of location and natural conditions of the construction survey site, characteristics and scope of the construction.
- Load of completed construction surveys.
- Experimented and analyzed result and data from construction survey.
- The opinions, notes and/or suggestions (if any).
- Conclusions and proposed solutions.
- Appendixes.
Best regards!