Wastewater Treatment Plant, Wastewater Treatment Station (WWTS) according to the National Technical Regulation

How are wastewater treatment plants and wastewater treatment stations (XLNT) regulated according to the national technical standards? I hope to receive a response on this issue from the editorial board. Thank you.

According to the National Technical Regulations on Construction Planning issued with Circular 22/2019/TT-BXD (effective from July 1, 2020), the wastewater treatment plants, wastewater treatment stations (WTS) regulations are as follows:

- Urban, medical, industrial park, and craft village domestic wastewater must be treated to meet the regulations in environmental standards for wastewater before being discharged to receiving sources and other relevant standards; Waste sludge from the drainage system must be collected, treated as per regulations, or transported to centralized solid waste treatment facilities;

- The location of newly planned wastewater treatment plants, WTS should prioritize planning at the end of the receiving water flow after treatment, at the end of the city's main wind direction, in an area with sufficient land for future expansion; The location of the wastewater discharge point must comply with the legal regulations on water resource management;

- In the case that wastewater treatment plants, WTS must be placed at the water source or the main wind direction of the city, the environmental safety distance (ESD) in Table 2.23 must be increased by at least 1.5 times;

- The land area for constructing newly planned wastewater treatment plants, WTS is determined based on capacity, treatment technology, or calculation according to the chosen standards but must ensure not to exceed the target of 0.2 ha/1,000 m^3^/day.

NOTE: The controlled land area index for constructing wastewater treatment plants, WTS does not include the reservoir area, stabilized wastewater area after treatment, sludge drying yard, expansion reserve area (if any), and the organizational area of the ESD of the wastewater treatment plant, WTS itself.

The above is the content regarding wastewater treatment plants, WTS according to the National Technical Regulations. For more information on this matter, you can refer to Circular 22/2019/TT-BXD.

Best regards!

Related Posts
LawNet
Guidelines on criteria for identifying temporary and dilapidated houses in Vietnam in 2025
LawNet
What is the template of Application for a construction permit for detached house in Vietnam in 2025?
LawNet
What is the template of the Application for reissue of construction permit for detached house in 2025 in Vietnam?
LawNet
What is the template of the Report for appraising the feasibility study for construction investment in accordance with Decree 175 in Vietnam?
LawNet
Promulgation of Circular 11/2024/TT-BXD on codes, title standards; standards and conditions for promotion consideration of public employees in the Construction sector in Vietnam
LawNet
Will the Urban and Rural Planning Law 2024 in Vietnam be effective from July 1, 2025?
LawNet
From January 1, 2025, will the district-level town Phong Dien beestablished under Hue city?
LawNet
From January 1, 2025, is it correct that Hue will become a central-affiliated city of Vietnam?
LawNet
Where is Ly Son Island? What are detailed regulations on striving for Ly Son island district to become a center by 2030?
LawNet
Promulgation of Circular 94/2024/TT-BQP providing detailed provisions on certain articles of the Law on Housing in the People's Army of Vietnam
Lượt xem: 0
Latest Post

Đơn vị chủ quản: Công ty THƯ VIỆN PHÁP LUẬT.
Chịu trách nhiệm chính: Ông Bùi Tường Vũ - Số điện thoại liên hệ: 028 3935 2079
P.702A , Centre Point, 106 Nguyễn Văn Trỗi, P.8, Q. Phú Nhuận, TP. HCM;