The form of report on management of construction investment activities in 2023 in Vietnam

What are regulations on the latest form of report on management of construction investment activities in 2023 in Vietnam? - Question from Thanh Quynh (Da Nang).

The form of report on management of construction investment activities in 2023 in Vietnam

Pursuant to Clasue 3 Article 8 of the Circular 01/2023/TT-BXD stipulating the form of report on management of construction investment activities in 2023 as follows:

Report on management of construction investment activities

...

3. Required content: based on Form No. 001 and Form No. 002 of the Appendix issued with this Circular.

Form No. 001. Report on management of construction investment activities (about the appraisal of the construction investment feasibility study report and the construction design and implementation after the basic design) of the appraisal agency under the Ministry of specialized construction management

ASSESSMENT AGENCY 1
-------

SOCIALIST REPUBLIC OF VIETNAM
Independence - Freedom - Happiness
---------------

Number: ..../BC-Abbreviated name of reporting agency

.…., day ..... month ..... year .….

 

REPORT

Status of construction investment management
(about the appraisal of the construction investment feasibility study report and the construction design and implementation after the basic design)

I. General assessment of the management of construction investment activities

II. Specific information:

Number of applications for appraisal by type of capital source

Construction investment feasibility study report

Construction design deploys after basic design

Total number of projects appraised

Total investment (million VND)

Total Appraisals

Estimated value of construction work (million VND)

Public Investment Capital

       

Foreign State Capital Public Investment

       

III. Difficulties, problems, suggestions.

 


Where to receive:
- Name of the agency receiving the report;
- Save: VT,...

HEAD OF AGENCY
(Signature, full name, position and seal)

________________________________

[1] Name of the specialized construction agency under the Ministry of Construction Management.

 

Form No.002. Report on management of construction investment activities (about the appraisal of construction investment feasibility study report and construction design, implementation after basic design and issuance of operation license) construction for foreign contractors) of the Provincial People's Committee

PROVINCE/CITY People's Committee
-------

SOCIALIST REPUBLIC OF VIETNAM
Independence - Freedom - Happiness
---------------

Number: .../BC-Abbreviated name of reporting agency

…., day month Year ….

 

REPORT

Management of construction investment activities

I. General assessment of the management of construction investment activities

II. Specific information

1. Regarding the appraisal of the construction investment feasibility study report and the construction design, following the basic design:

Specialized Construction Management Department

Construction investment feasibility study report

Construction design deploys after basic design

Public Investment Capital (Unit: Number of times of dossiers being appraised)

Foreign state capital for public investment (Unit: Number of times of dossiers being appraised)

Other capital (Unit: Number of times of application is appraised)

Total investment (million VND) *

Total number of appraised (Unit: Number of times of dossiers being appraised)

Estimated value of construction work (million VND)**

Facility construction

           

Transportation facilities

           

Department of Agriculture and Rural Development

           

Industrial and commercial facilities

           

2. Regarding the number of construction permits granted to foreign contractors in the year:...

III. Difficulties, problems, suggestions:...

 


Where to receive:
- Name of the agency receiving the report;
- Retain: VT.

HEAD OF THE AGENCY…
(Signature, full name, position and seal)

 

* and **: The aggregate requirement is only required for projects with total investment/construction cost estimates using public investment capital and foreign state investment capital.

What is the deadline for submitting the report on management of construction investment activities in 2023 in Vietnam?

Pursuant to Article 8 of the Circular 29/2022/TT-BLĐTBXH stipulating the deadline for submitting the report on management of construction investment activities in 2023 as follows:

Report on management of construction investment activities

1. Reporting basis: According to the provisions of Clause 8, Article 109 of the Government's Decree No. 15/2021/ND-CP dated March 3, 2021 on management of construction investment projects.

2. Subjects of the report, the agency receiving the report, the process and time limit for sending the report:

Ministries managing specialized construction works and provincial People's Committees shall send reports to the Ministry of Construction no later than December 20 of each year for summarization and monitoring.

3. Report required content: According to Form No. 001 and Form No. 002 of the Appendix issued with this Circular.

4. Reporting frequency: Annually.

5. Time to close report data: According to the provisions of Clause 4, Article 12 of Decree No. 09/2019/ND-CP.

Thus, the deadline for submitting the report on management of construction investment activities for synthesis and monitoring is before December 20, 2023.

What are prohibited acts in construction in Vietnam?

Pursuant to Article 12 of the Law on Construction in 2014 (amended by Clause 64.c Article 1 of the Law on Amendments to the Law on Construction in 2020) stipulating prohibited acts in construction in Vietnam as follows:

- Deciding on construction investment in contravention of this Law.

- Starting construction when the conditions therefor prescribed in this Law are not fully met.

- Constructing works in non-construction zones ; constructing works in encroachment upon the protection corridors of national defense, security, traffic or irrigation works, dykes, energy facilities, historical-cultural relic areas and protection zones of other works prescribed by law; constructing works in areas prone to landslide, sweeping flood or flash flood, except works built to overcome these phenomena.

- Constructing works at variance with construction master plan, except cases with construction permits with a definite term; in encroachment of construction boundaries or construction levels; constructing works at variance with granted construction permits.

- Formulating, appraising and approving designs and cost estimates of construction works using public investment funds, non-public investment state funds in contravention of this Law.

- Contractors participating in construction activities when failing to fully satisfy the capacity conditions for carrying out construction activities.

- Project owners selecting contractors that fail to fully meet the capacity conditions for conducting construction activities.

- Constructing works not in compliance with the selected standards and technical regulations to be applied to works.

- Manufacturing and using building materials which cause harms to community health and environment.

- Violating regulations on labor safety and assets, fire and explosion prevention and fighting, security, order and environmental protection in construction.

- Using works against their purposes and utility; building annexes or lean-tos encroaching upon areas and spaces lawfully managed or used by other organizations or individuals or upon public areas and common-use areas.

- Giving and taking bribe in construction investment activities; abusing other legal persons to participate in construction activities; committing manipulation and collusion to falsify the results of project formulation, surveys, designs or supervision of construction.

- Abusing positions and powers to violate the law on construction; covering up and handling late acts in violation the law on construction.

- Obstructing lawful construction investment activities.

Best regards!

Related Posts
LawNet
Promulgation of Circular 94/2024/TT-BQP providing detailed provisions on certain articles of the Law on Housing in the People's Army of Vietnam
LawNet
What is construction permit according to the law in Vietnam? What documents are required for Application for a construction permit for detached houses in Vietnam?
LawNet
Is a permit required for relocating a construction project in Vietnam? What documents are included in the Application for a construction relocation permit in Vietnam?
LawNet
What day is November 8? What are contents of Management Regulations according to urban planning project, urban design in Vietnam?
LawNet
Which Construction Price Indices are Determined by Project, Type of Project?
LawNet
Legal Basis for National Land Use Planning and Planning under the Latest Regulations
LawNet
Period of Land Use Planning and Plan According to the Latest Regulations
LawNet
What is a Rural Market?
LawNet
What is a Temporary Market?
LawNet
What is a Public Market?
Lượt xem: 0
Latest Post

Đơn vị chủ quản: Công ty THƯ VIỆN PHÁP LUẬT.
Chịu trách nhiệm chính: Ông Bùi Tường Vũ - Số điện thoại liên hệ: 028 3935 2079
P.702A , Centre Point, 106 Nguyễn Văn Trỗi, P.8, Q. Phú Nhuận, TP. HCM;