The construction project management costs in Vietnam

According to the new regulations on construction investment costs, what are the construction project management costs in Vietnam? Please get back to me.

The construction project management costs in Vietnam (Image from the Internet)

According to the provisions of Article 21 of Decree 68/2019/ND-CP (effective October 1, 2019) stipulating construction project management costs:

1. Project management costs are necessary expenditures on performance of project management tasks from project preparation, project execution, construction completion and project inauguration.

2. Project management costs include salaries of project managers; wages of employees under contracts; allowances, bonuses; collective benefits; contributions (social insurance; health insurance; unemployment insurance; trade union fees, and other payments made by individuals receiving salaries from the project); cost of application of science and technology, work information system management, provision of advanced training for project managers; payment for public services; office supplies; communications, propagation; organization of relevant conventions; business trip allowances; lease; repair, purchase of assets serving project management; other costs, and cost contingency.

3. Project management costs are determined according to a rate (%) set by the Ministry of Construction or according to an estimate that suits the project management manner, duration, scale of the project, and characteristics of the project management tasks.

4. With regard to projects funded by external-source state capital and special projects, if the investor hires a project management consultant, then the project management consultancy costs shall be determined according to the contents, quantity of project management tasks, and agreement between the investor and the advisory organization in the project management contract.

5. With regard to small-scale renovation or repair projects that are defined in the Decree on construction project management and participated by the community, and the investor may make use of the whole apparatus to manage the project, the project management costs shall be determined according to estimate as prescribed in Clause 3 of this Article.

Above are the regulations on construction project management costs.

Best regards!

Related Posts
LawNet
Guidelines on criteria for identifying temporary and dilapidated houses in Vietnam in 2025
LawNet
What is the template of Application for a construction permit for detached house in Vietnam in 2025?
LawNet
What is the template of the Application for reissue of construction permit for detached house in 2025 in Vietnam?
LawNet
What is the template of the Report for appraising the feasibility study for construction investment in accordance with Decree 175 in Vietnam?
LawNet
Promulgation of Circular 11/2024/TT-BXD on codes, title standards; standards and conditions for promotion consideration of public employees in the Construction sector in Vietnam
LawNet
Will the Urban and Rural Planning Law 2024 in Vietnam be effective from July 1, 2025?
LawNet
From January 1, 2025, will the district-level town Phong Dien beestablished under Hue city?
LawNet
From January 1, 2025, is it correct that Hue will become a central-affiliated city of Vietnam?
LawNet
Where is Ly Son Island? What are detailed regulations on striving for Ly Son island district to become a center by 2030?
LawNet
Promulgation of Circular 94/2024/TT-BQP providing detailed provisions on certain articles of the Law on Housing in the People's Army of Vietnam
Lượt xem: 0
Latest Post

Đơn vị chủ quản: Công ty THƯ VIỆN PHÁP LUẬT.
Chịu trách nhiệm chính: Ông Bùi Tường Vũ - Số điện thoại liên hệ: 028 3935 2079
P.702A , Centre Point, 106 Nguyễn Văn Trỗi, P.8, Q. Phú Nhuận, TP. HCM;