Sample report on completion of construction supervision of bidding packages/phases/work items/construction works in Vietnam?

What are regulations on sample report on completion of construction supervision of bidding packages/phases/work items/construction works in Vietnam? What are regulations on sample periodical report on construction supervision of works/work items? What are regulations on sample notice of commencement of construction of work items, construction works in Vietnam?

Thank you!

What are regulations on sample report on completion of construction supervision of bidding packages/phases/work items/construction works in Vietnam?

Pursuant to the Appendix IVB issued together with the Decree 06/2021/ND-CP stipulating sample report on completion of construction supervision of bidding packages/phases/work items/construction works in Vietnam as follows:

…(1)…
-------

SOCIALIST REPUBLIC OF VIETNAM
Independence - Freedom - Happiness
---------------

Number: ……./……

……. , day……. month……. year………

REPORT OF COMPLETION OF CONSTRUCTION SUPERVISION OF

BIDDING PACKAGES/PHASES/WORK ITEMS/CONSTRUCTION WORKS

To: ………….(2)………….

……(1)....report on construction supervision....(3).... as follows:

1. Scale of works:

a) Description of the scale and function of the work: the main technical parameters, the main functions of the parts or work items;

b) Assessment of the suitability of the work's scale and functions with the construction permit (for works requiring a construction permit), construction design, technical instructions, construction methods, approved safety measures and technical regulations and standards applicable to the works.

2. Assessment of the suitability of the construction contractor's capacity with the bid dossier and construction contract.

3. Evaluation of completed work volume and progress, construction organization and assurance of labor safety in construction work.

4. Evaluation of testing and inspection of construction materials, products, components and equipment installed in the works according to the approved test plan.

5. Evaluation of the organization and results of inspection, observation and control experiment (if any).

6. Evaluation of the organization of the acceptance test of construction work, phase acceptance test (if any).

7. Design of changes and the appraisal and approval of the adjusted design during the construction process (if any).

8. Shortcomings, defects in quality, work incidents in the course of work construction (if any) and assessment of causes, measures and remedial results according to regulations.

9. Assessment of conformity of quality management records as prescribed.

10. Assessment of compliance with regulations of law on environment, law on fire prevention and fighting and other relevant laws (if any).

11. Assessment of the conformity of the operation process, the construction maintenance process according to regulations.

12. Evaluation of conditions for acceptance of completed bidding packages, stages, work items and construction works.

CHAIRMAN
(Signature, full name)

LEGAL REPRESENTATIVE OF
…..(1)….
(Sign and seal)

Note:

(1) Name of the organization performing construction supervision.

(2) Investor's name.

(3) Name of the package/phase/work item/construction work.

What are regulations on sample periodical report on construction supervision of works/work items?

Pursuant to the Appendix IVA issued together with the Decree 06/2021/ND-CP stipulating sample periodical report on construction supervision of works/work items as follows:

…(1)…
-------

SOCIALIST REPUBLIC OF VIETNAM
Independence - Freedom - Happiness
---------------

Number: ……./……

……. , day……. month……. year………

SAMPLE PERIODICAL REPORT ON CONSTRUCTION SUPERVISION OF WORKS/WORK ITEMS

To: …………(2)…….

……(1)....report on construction supervision of works/work items ....(3).... from …… to …… as follows:

1. Assessment of the suitability of the work's scale and functions with the construction permit (for works requiring a construction permit), construction design, technical instructions, construction methods, and measures. approved safety measures and technical regulations and standards applicable to the works.

2. Assessment of the suitability of capacity of construction contractors compared with bid documents and construction contracts:

a) Name of the construction unit;

b) Assessment of the suitability of the capacity of the project leader or the contractor's project manager, the person in charge of construction techniques directly compared with the construction contract regulations and the provisions of law;

c) Summary of statistics and evaluation of the conformity of machinery and equipment for construction in the reporting period compared with the construction contract.

3. Evaluation of the volume and progress of work completed in the reporting period, the organization of construction and assurance of labor safety in the construction of works:

a) Work volume completed in the reporting period. Workload has been accepted. Compare with the overall construction progress and cause of delay (if any);

b) Evaluation of construction organization compared with approved construction methods. Changes in construction methods (if any);

c) Evaluation of the implementation of the contents of the approved safety assurance plan.

4. Statistics of experimental work performed in the reporting period on the number of experimental results for each type of experiment. Evaluate the quality control of testing and inspection of materials, construction products, components and equipment installed in the works according to the approved test plan.

5. Statistics of construction works tested and accepted in the reporting period, the pre-acceptance work of the period (if any).

6. Statistics of design changes on the construction site during the reporting period.

7. Statistics of shortcomings, defects in quality, construction incidents (4) in the reporting period (if any); shortcomings and defects in quality have been remedied during the reporting period. Assessment of causes, measures and remedial results according to regulations.

8. Proposals, recommendations on progress, personnel, design and other technical issues.

 

CHAIRMAN
(Signature, full name)

Note

(1) Name of the organization performing construction supervision.

(2) Name of the investor.

(3) Name of work item/construction work.

(4) In case there is a construction incident in the reporting period, the report shall be enclosed with a dossier of work incident settlement as prescribed.

What are regulations on sample notice of commencement of construction of work items, construction works in Vietnam?

Pursuant to the Appendix V issued together with the Decree 06/2021/ND-CP stipulating sample notice of commencement of construction of work items, construction works in Vietnam as follows:

…(1)…
-------

SOCIALIST REPUBLIC OF VIETNAM
Independence - Freedom - Happiness
---------------

Number: ……./……

……. , date ……. month ……. year …………

 

NOTICE OF COMMENCEMENT OF CONSTRUCTION OF WORK ITEMS, CONSTRUCTION WORKS

Dear:

………….. (2) …………

………….. (3) …………

…… (1) …… report on the commencement of construction of work items, construction works as follows:

1. Name of work items, construction works: …….. under project …………..

2. Construction site: ……………………………………………………..

3. Name and address of the investor: ……………………………………………………

4. Name and contact phone number of the person in charge directly : …………………… ..

5. Scale of work items, construction works (specify the size, main technical parameters and usability of the work items, construction works).

6. List of main contractors and sub-contractors (if any): (general contractors, main contractors: construction survey, construction design, construction, construction supervision, project management).

7. Construction date and completion date (expected).


Receiving place:
- As above;
- Save …;
- Dossier attached(4)


LEGAL REPRESENTATIVE OF INVESTORS

(Signature, full name, position and seal of legal entity)

Notes :

(1) Name of the investor.

(2) Name of the state management agency in charge of construction g in the locality where the work is to be built.

(3) Name of the specialized construction agency that inspects the pre-acceptance test of the construction work as prescribed in Clause 2, Article 24 of this Decree in case the works are subject to the pre-acceptance inspection as prescribed in Clause 1, Article 24 of this Decree.

(4) The cases specified at Points b, e, h and i, Clause 2, Article 89 of Law No. 50/2014/QH 13 are amended and supplemented in Clause 30, Article 1 of Law No. 62/2020/ QH14 enclosed with construction design documents; In the case specified at Point g, Clause 2, Article 89 of Law No. 50/2014/QH13, as amended and supplemented in Clause 30, Article 1 of Law No. 62/2020/QH14, the attached dossier includes: design dossier construction and documents proving the satisfaction of conditions for construction permits.

Best regards!

Related Posts
LawNet
Guidelines on criteria for identifying temporary and dilapidated houses in Vietnam in 2025
LawNet
What is the template of Application for a construction permit for detached house in Vietnam in 2025?
LawNet
What is the template of the Application for reissue of construction permit for detached house in 2025 in Vietnam?
LawNet
What is the template of the Report for appraising the feasibility study for construction investment in accordance with Decree 175 in Vietnam?
LawNet
Promulgation of Circular 11/2024/TT-BXD on codes, title standards; standards and conditions for promotion consideration of public employees in the Construction sector in Vietnam
LawNet
Will the Urban and Rural Planning Law 2024 in Vietnam be effective from July 1, 2025?
LawNet
From January 1, 2025, will the district-level town Phong Dien beestablished under Hue city?
LawNet
From January 1, 2025, is it correct that Hue will become a central-affiliated city of Vietnam?
LawNet
Where is Ly Son Island? What are detailed regulations on striving for Ly Son island district to become a center by 2030?
LawNet
Promulgation of Circular 94/2024/TT-BQP providing detailed provisions on certain articles of the Law on Housing in the People's Army of Vietnam
Lượt xem: 0
Latest Post

Đơn vị chủ quản: Công ty THƯ VIỆN PHÁP LUẬT.
Chịu trách nhiệm chính: Ông Bùi Tường Vũ - Số điện thoại liên hệ: 028 3935 2079
P.702A , Centre Point, 106 Nguyễn Văn Trỗi, P.8, Q. Phú Nhuận, TP. HCM;