Based on Clause 5, Article 19 of Decree 37/2015/ND-CP regarding payment regulations:
For lump-sum contracts: Payments are made according to the percentage of the contract price or the price of the project, project items, and work volume corresponding to the payment stages agreed upon by the parties in the contract. Detailed confirmation of the completed volume is not required upon payment.
The above is the regulation on payment for lump-sum contracts pursuant to the aforementioned regulation.
Sincerely!

Guidelines on criteria for identifying temporary and dilapidated houses in Vietnam in 2025

What is the template of Application for a construction permit for detached house in Vietnam in 2025?

What is the template of the Application for reissue of construction permit for detached house in 2025 in Vietnam?

What is the template of the Report for appraising the feasibility study for construction investment in accordance with Decree 175 in Vietnam?

Promulgation of Circular 11/2024/TT-BXD on codes, title standards; standards and conditions for promotion consideration of public employees in the Construction sector in Vietnam

Will the Urban and Rural Planning Law 2024 in Vietnam be effective from July 1, 2025?

From January 1, 2025, will the district-level town Phong Dien beestablished under Hue city?

From January 1, 2025, is it correct that Hue will become a central-affiliated city of Vietnam?

Where is Ly Son Island? What are detailed regulations on striving for Ly Son island district to become a center by 2030?

Promulgation of Circular 94/2024/TT-BQP providing detailed provisions on certain articles of the Law on Housing in the People's Army of Vietnam