Fees for appraisal of technical design in Vietnam in 2020
Pursuant to Article 3 of Circular 34/2020/TT-BTC and Circular 210/2016/TT-BTC stipulates:
From May 5, 2020, to the end of December 31, 2020, the collection and submission rate for technical design appraisal fees will be 50% of the fee rate specified in the Fee Schedule issued with Circular No. 210/2016/TT-BTC.
The fee rates according to Circular 210/2016/TT-BTC are as follows:
1. Fees for appraisal of technical design and construction estimates (Appraisal of technical design, construction cost appraisal for three-step design; construction drawing design, project cost appraisal for two-step design)
Unit: Percentage
No |
Type of Works |
Construction Costs (excluding VAT) in the approved project estimate or bid package estimate (billion VND) |
||||||||
≤15 |
50 |
100 |
200 |
500 |
1.000 |
2.000 |
5.000 |
8.000 |
||
1 |
Civil works |
0,160 |
0,106 |
0,083 |
0,062 |
0,046 |
0,038 |
0,028 |
0,021 |
0,018 |
2 |
Industrial works |
0,185 |
0,121 |
0,094 |
0,072 |
0,055 |
0,041 |
0,033 |
0,023 |
0,020 |
3 |
Transportation works |
0,106 |
0,068 |
0,054 |
0,041 |
0,031 |
0,024 |
0,020 |
0,014 |
0,012 |
4 |
Agricultural and rural development works |
0,117 |
0,076 |
0,060 |
0,046 |
0,035 |
0,026 |
0,022 |
0,016 |
0,014 |
5 |
Technical infrastructure works |
0,122 |
0,082 |
0,062 |
0,047 |
0,037 |
0,029 |
0,024 |
0,017 |
0,014 |
2. Fees for appraisal of technical design and construction estimates when the specialized construction agency organizes consultancy institutions and individuals to jointly appraise (Technical design appraisal, construction project appraisal for three-step design cases; construction drawing design, cost estimate appraisal for two-step design cases)
Unit: Percentage
No. |
Type of Works |
Construction Costs (excluding VAT) in the approved project estimate or bid package estimate (billion VND) |
||||||||
≤15 |
50 |
100 |
200 |
500 |
1. 000 |
2.000 |
5.000 |
8.000 |
||
1 |
Civil works |
0,0480 |
0,0318 |
0,0249 |
0,0186 |
0,0138 |
0,0114 |
0,0084 |
0,0063 |
0,0054 |
2 |
Industrial works |
0,0555 |
0,0363 |
0,0282 |
0,0216 |
0,0165 |
0,0123 |
0,0099 |
0,0069 |
0,006 |
3 |
Transportation works |
0,0318 |
0,0204 |
0,0162 |
0,0123 |
0,0093 |
0,0072 |
0,006 |
0,0042 |
0,0036 |
4 |
Agricultural and rural development works |
0,0351 |
0,0228 |
0,0180 |
0,0138 |
0,0105 |
0,0078 |
0,0066 |
0,0048 |
0,0042 |
5 |
Technical infrastructure works |
0,0366 |
0,0246 |
0,0186 |
0,0141 |
0,0111 |
0,0087 |
0,0072 |
0,0051 |
0,0042 |
=> Therefore, from May 5, 2020, to December 31, 2020, the technical design appraisal fee will be reduced to 50% compared to the above fee schedule. You should refer to specific construction categories to determine the fee.
This is the content for your reference.
Respectfully!