Can employer have the right to temporarily suspend the contract performance when the contractor fails to meet requirements for contract progress as agreed in Vietnam?

Can employer have the right to temporarily suspend the contract performance when the contractor fails to meet requirements for contract progress as agreed in Vietnam? 

My side is a contractor for a construction project. But now the construction progress has been slower than agreed. Now we want to suspend the performance of the contract, is it possible? How many days in advance is the notice required in Vietnam?

Can employer have the right to temporarily suspend the contract performance when the contractor fails to meet requirements for contract progress as agreed in Vietnam?

Pursuant to Clause 2, Article 40 of Decree 37/2015/ND-CP stipulating the parties to the contract are entitled to temporarily suspend the contract in the following cases:

a) The employer has the right to temporarily suspend the contract performance when the contractor fails to meet requirements for quality, labor safety and contract progress as agreed in the contract.

b) The contractor has the right to temporarily suspend the contract performance and prolong the contract progress when the employer is in breach of payment terms, specifically no adequate payment is made to the contractor as agreed after 28 days since the payment deadline as prescribed in Clause 10, Article 19 hereof except otherwise as agreed by the two parties; no payment guarantee is made for quantity of work to be executed.

Thus, if the construction progress is not carried out as agreed, the employer has the right to suspend the contract performance in Vietnam.

How many days in advance is the notice required in Vietnam?

In Clause 3, Article 40 of Decree 37/2015/ND-CP, the deadline for notification of contract suspension is as follows:

3. Before one party temporarily suspends the contract performance, a written notice must be made to the other party 28 days in advance with reasons for temporary suspension being specified; the employer and contractor shall be responsible for carrying out negotiations to continue to maintain agreements as signed in the contract except force majeure events.

In case one party fails to make a notice about temporary suspension or reasons specified are found contrary to the signed contract, it shall be responsible for making compensation for losses caused to the other party.

Therefore, the notice of contract suspension must be notified at least 28 days in advance, otherwise, compensation will be required as prescribed.

Best Regards!

Related Posts
LawNet
Guidelines on criteria for identifying temporary and dilapidated houses in Vietnam in 2025
LawNet
What is the template of Application for a construction permit for detached house in Vietnam in 2025?
LawNet
What is the template of the Application for reissue of construction permit for detached house in 2025 in Vietnam?
LawNet
What is the template of the Report for appraising the feasibility study for construction investment in accordance with Decree 175 in Vietnam?
LawNet
Promulgation of Circular 11/2024/TT-BXD on codes, title standards; standards and conditions for promotion consideration of public employees in the Construction sector in Vietnam
LawNet
Will the Urban and Rural Planning Law 2024 in Vietnam be effective from July 1, 2025?
LawNet
From January 1, 2025, will the district-level town Phong Dien beestablished under Hue city?
LawNet
From January 1, 2025, is it correct that Hue will become a central-affiliated city of Vietnam?
LawNet
Where is Ly Son Island? What are detailed regulations on striving for Ly Son island district to become a center by 2030?
LawNet
Promulgation of Circular 94/2024/TT-BQP providing detailed provisions on certain articles of the Law on Housing in the People's Army of Vietnam
Lượt xem: 0
Latest Post

Đơn vị chủ quản: Công ty THƯ VIỆN PHÁP LUẬT.
Chịu trách nhiệm chính: Ông Bùi Tường Vũ - Số điện thoại liên hệ: 028 3935 2079
P.702A , Centre Point, 106 Nguyễn Văn Trỗi, P.8, Q. Phú Nhuận, TP. HCM;