Can employer have the right to temporarily suspend the contract performance when the contractor fails to meet requirements for contract progress as agreed in Vietnam?

Can employer have the right to temporarily suspend the contract performance when the contractor fails to meet requirements for contract progress as agreed in Vietnam? 

My side is a contractor for a construction project. But now the construction progress has been slower than agreed. Now we want to suspend the performance of the contract, is it possible? How many days in advance is the notice required in Vietnam?

Can employer have the right to temporarily suspend the contract performance when the contractor fails to meet requirements for contract progress as agreed in Vietnam?

Pursuant to Clause 2, Article 40 of Decree 37/2015/ND-CP stipulating the parties to the contract are entitled to temporarily suspend the contract in the following cases:

a) The employer has the right to temporarily suspend the contract performance when the contractor fails to meet requirements for quality, labor safety and contract progress as agreed in the contract.

b) The contractor has the right to temporarily suspend the contract performance and prolong the contract progress when the employer is in breach of payment terms, specifically no adequate payment is made to the contractor as agreed after 28 days since the payment deadline as prescribed in Clause 10, Article 19 hereof except otherwise as agreed by the two parties; no payment guarantee is made for quantity of work to be executed.

Thus, if the construction progress is not carried out as agreed, the employer has the right to suspend the contract performance in Vietnam.

How many days in advance is the notice required in Vietnam?

In Clause 3, Article 40 of Decree 37/2015/ND-CP, the deadline for notification of contract suspension is as follows:

3. Before one party temporarily suspends the contract performance, a written notice must be made to the other party 28 days in advance with reasons for temporary suspension being specified; the employer and contractor shall be responsible for carrying out negotiations to continue to maintain agreements as signed in the contract except force majeure events.

In case one party fails to make a notice about temporary suspension or reasons specified are found contrary to the signed contract, it shall be responsible for making compensation for losses caused to the other party.

Therefore, the notice of contract suspension must be notified at least 28 days in advance, otherwise, compensation will be required as prescribed.

Best Regards!

Related Posts
lawnet.vn
Năm 2024, hồ sơ đề nghị cấp giấy phép xây dựng công trình quảng cáo gồm những giấy tờ gì?
lawnet.vn
Chính thức có Thông tư 05/2024/TT-BXD quy định chi tiết một số điều của Luật Nhà ở?
lawnet.vn
Hồ sơ đề nghị cấp giấy phép xây dựng đối với nhà ở riêng lẻ gồm những giấy tờ gì?
lawnet.vn
Hồ sơ đề nghị cấp lại giấy phép xây dựng gồm những giấy tờ gì? Giấy phép xây dựng công trình bị thu hồi khi nào?
lawnet.vn
Thủ tục cấp chứng chỉ năng lực hoạt động xây dựng mới nhất 2024?
lawnet.vn
Hợp đồng xây dựng được điều chỉnh trong trường hợp nào?
lawnet.vn
Năm 2024, việc phá dỡ công trình xây dựng được thực hiện trong các trường hợp nào?
lawnet.vn
Điều kiện cấp chứng chỉ hành nghề khảo sát xây dựng 2024 là gì?
lawnet.vn
Đã có Thông tư hướng dẫn thi đua khen thưởng trong ngành Xây dựng được áp dụng từ ngày 01/7/2024?
lawnet.vn
Đối tượng nào được xét tặng Kỷ niệm chương Vì sự nghiệp Xây dựng từ ngày 01/7/2024?
Lượt xem: 0
Latest Post

Đơn vị chủ quản: Công ty THƯ VIỆN PHÁP LUẬT.
Chịu trách nhiệm chính: Ông Bùi Tường Vũ - Số điện thoại liên hệ: 028 3935 2079
P.702A , Centre Point, 106 Nguyễn Văn Trỗi, P.8, Q. Phú Nhuận, TP. HCM;