What are regulations on cover of activity log of an investment project using state budget capital in Vietnam?

What are regulations on cover of activity log of an investment project using state budget capital in Vietnam? What are regulations on cover of supervisory log to monitor implementation of investment projects using state budget capital in Vietnam? 

Please advise. Thankyou.

What are regulations on cover of activity log of an investment project using state budget capital in Vietnam?

In the form No. 1, Appendix 1 issued together with Circular 24/2020/TT-BTTTT stipulating cover of activity log of an investment project using state budget capital as follows:

ACTIVITY LOG

NUMBER:…………………….

1. Project name : ............................ ................................. ..........

2. Item name : ............................ ................................. .........

3. Deployment location : ................................................................. ................................. ...

4. Investor : ............................ ................................. ..........

Full name of Investor's representative: ................................................................................. ..............................

5. Project management board or project management consulting organization : ................................................................. .........

Full name of the representative of the Project Management Board or the project management consulting organization:……………………………………………………. …………..

6. Deployment contractor : ................................................................................. ................................. ...

Name and address of person in charge of implementation ..................................................................................................... ..............................

7. Deployment supervisory unit (if any) : ..................................................... ..........

Full name of the person in charge of supervisory the implementation ..................................................................... ............

8. Organizations and individuals for detailed design and cost estimates : ............................................................................ ..........

9. Deployment Information

Deployment contract number: ……………………………………………………. Day.....................................

Contract start date..................................... Actual ………….

Contract end date ..................................................................................... ......... Reality...............

This book includes:……………………. pages, numbered from 01 to ………….

Full name and signature of the person in charge of the deployment and management of the deployment diary:

Nguyen Van A

Signature:

Full name and signature of the person in charge of supervisory the implementation (if any):

Nguyen Van B

Signature:

 

 

..., date....month...year....
Representative of the implementing contractor
(Signature, full name, position, stamp)

 Form No. 1.1. Deployment log content 1

Deployment log content

I. Contents of implementation work

No

Deployment time

Contents of implementation work

Record progress, actual deployment situation, this is the basic part of the diary. In this section, it is necessary to specify the implementation personnel, the implementation status of each type of work, the start time and reflect in detail the entire implementation process, briefly describe the process, implementation method, the situation of materials, equipment, incidents, damage, violations, differences, other arising problems and measures to overcome and handle; comments, suggestions...

Opinion and signature of the representative of the unit supervising the implementation (if any) for the contents of the implementation.

Opinion and confirmation signature of the representative of the detailed design consulting unit during the implementation of author supervision (if any).

...

...

...

II. Other contents (if any)

................................. ................................. ..............................

................................. ................................. ..............................

................................. ................................. ..............................

................................. ................................. ..............................

_______________

Note: Based on the reference to this form, the units can add other necessary information to the implementation log to suit the actual situation of project implementation.

What are regulations on cover of supervisory log to monitor implementation of investment projects using state budget capital in Vietnam? 

In the form No. 2, Appendix 1 issued together with Circular 24/2020/TT-BTTTT stipulating cover of supervisory log to monitor implementation of investment projects using state budget capital is specified as follows:

IMPLEMENTATION SUPERVISORY LOG

NUMBER:…………………….

1. Project name : ............................ ................................. ..........

2. Item name : ............................ ................................. .........

3. Deployment location : ................................................................. ................................. ...

4. Investor : ............................ ................................. ..........

Full name of Investor's representative: ................................................................................. ..............................

5. Project Management Board or project management consulting organization (if any) : .................................................................

Full name of the representative of the Project Management Board or the project management consulting organization: ...........

6. Deployment contractor : ................................................................................. ................................. ...

Full name of person in charge of implementation: ..................................................................................... ..............................

7. Unit overseeing the implementation : ................................................................................. ................................

Full name of the person in charge of supervisory the implementation:................................................................................ .............

8. Organizations and individuals for detailed design and cost estimates : ............................................................................ ..........

9. Information on supervisory the implementation

Contract to supervise the implementation of implementation No: ............................................................ .. Day ……………

Start date of implementation under the contract: ................................. Actual date ………… ……

Date of commencement of supervisory of contract implementation: ............

Closing date of implementation under the contract: ................................................................................. Actual date………….

End date of supervisory of implementation under the contract: ................. Actual date ........

This book includes: ……………………. pages, numbered from 01 to .........

Full name and signature of the person in charge of supervising the implementation, managing the implementation supervisory log:

Nguyen Van A

Signature:

 

 

…, date...month...year...
Representative of the unit
supervising the implementation
(Signature, full name, position, stamp)

 Form No. 2.1. Deployment supervisory log content 2

Contents of the implementation supervisory log

I. Contents of implementation and supervisory of implementation

No

Implementation supervisory time

Contents of the work of supervisory the implementation

This is the basic part of the supervisory log. In this section, it is required to specify the personnel supervising the implementation, the contents, developments and results of the supervisory of the work implementation corresponding to each implementation content of the implementing contractor; starting time and reflecting in detail the entire implementation process, the results of supervisory the implementation; deviations in the implementation process from the design signed by the representative of the unit overseeing the implementation.

...

...

II. Other contents (if any)

................................. ................................. ..............................

................................. ................................. ..............................

................................. ................................. ..............................

................................. ................................. ..............................

_______________

Note: Based on this form, units can add other necessary information to the implementation supervisory log to suit the actual situation of implementation supervisory.

 Form No. 2.2. Report on implementation supervisory results

SOCIALIST REPUBLIC OF VIETNAM Independence
- Freedom - Happiness
------------------

 

..., day month Year ...

 

REPORT ON SUPERVISORY RESULTS OF IMPLEMENTATION

Dear: Investor

1. General information of the project

- Name of project.

- Name of item, job.

- Name of owner.

- Deployment location.

- Name of the implementing contractor.

- Name of the detailed design consultancy unit.

- Name of the unit overseeing the implementation.

2. supervisory content

- Conditions for deployment.

- The compatibility of the contractor's capacity with the contract.

- The suitability of materials, information technology equipment, software before construction, installation, installation.

- supervisory content during implementation.

- Content supervisory deployment volume.

- Content supervisory the progress of implementation.

- Content of supervisory changes during implementation (if any).

- Other contents according to the implementation supervision contract (if any).

3. Conclusions and recommendations

4. Attached documents

- Supervisory log to monitor the implementation.

- Relevant minutes.

 

REPRESENTATIVE OF IMPLEMENTATION supervisory UNIT
(Signature, full name, position and seal)

 Best Regards!

Related Posts
LawNet
Has the Code of Conduct on Protecting Children in the Online Environment in 2025 in Vietnam been issued?
LawNet
What is the code of conduct for the protection of children in the online environment in Vietnam?
LawNet
Decree No. 163/2024/ND-CP detailing certain articles and measures for implementation of the Telecommunications Law in Vietnam
LawNet
Promulgation of Circular 25/2024/TT-BTNMT stipulating the procedures for developing the national land database in Vietnam
LawNet
Details of the Law on Data 2024 in Vietnam from July 1, 2025
LawNet
From December 25, 2024, are accounts for online games that are not verified by phone number in Vietnam allowed to play?
LawNet
What are types of website in Vietnam? Which types of website are not subject to licensing in Vietnam?
LawNet
Circular 50/2024/TT-NHNN stipulating the safety and security for providing online services in the banking sector in Vietnam
LawNet
What are cases of temporary suspension of domain names in Vietnam?
LawNet
What are regulations on classification of age groups for online video games in Vietnam?
Lượt xem: 0
Latest Post

Đơn vị chủ quản: Công ty THƯ VIỆN PHÁP LUẬT.
Chịu trách nhiệm chính: Ông Bùi Tường Vũ - Số điện thoại liên hệ: 028 3935 2079
P.702A , Centre Point, 106 Nguyễn Văn Trỗi, P.8, Q. Phú Nhuận, TP. HCM;