Sequence and procedures for assessment and approval of tasks and construction planning project in Vietnam

Sequence and procedures for assessment and approval of tasks and construction planning project in Vietnam
Lê Trương Quốc Đạt

What are the regulations on the sequence and procedures for assessment and approval of tasks and construction planning project in Vietnam? - Kim Phuong (Tien Giang, Vietnam)

Thủ tục thẩm định, phê duyệt nhiệm vụ và đồ án quy hoạch xây dựng

Sequence and procedures for assessment and approval of tasks and construction planning project in Vietnam (Internet image)

Regarding this issue, LawNet would like to answer as follows:

1. Sequence and procedures for assessment and approval of tasks and construction planning project in Vietnam

Sequence and procedures for assessment and approval of tasks and construction planning project in Vietnam according to Article 25 of Decree 44/2015/ND-CP (amended in Decree 72/2019/ND-CP) are as follows:

- Assessment and approval agencies:

+ The Ministry of Construction, People’s committees of provinces shall be responsible for making submission of the tasks and construction planning project to the Prime Minister for approval.

+ Organizer of construction planning shall be responsible for making submission of the tasks and construction planning to People’s committees at all levels for approval.

- Collect suggestions from state management agencies on the construction planning project during the assessment;

+ People’s committees of provinces shall be responsible for collecting suggestions from the Ministry of Construction before approval of general planning projects of purpose zones; zoning projects for purpose zone with size of over 200 ha

+ People’s committees of districts shall be responsible for collecting suggestions from Department of Construction Works Management before approval of construction planning projects within competence.

- During assessment of the tasks and construction planning projects, the assessment agencies shall be responsible for collecting suggestions from line management agencies at the same level, professional associations and relevant specialists.

- Result of assessment of the tasks and construction planning shall be dispatched to organizers of construction planning as foundations for completion of the project before submission to competent authority for approval.

2. Time for assessment and approval of construction planning project in Vietnam

Time for assessment and approval of construction planning project in Vietnam according to Article 26 of Decree 44/2015/ND-CP (amended in Decree 72/2019/ND-CP) is as follows:

- For planning of other zones, time for the assessment of the tasks is from 20 days and under, for approval from 15 days and under; time for assessment of the project is from 25 days and under, for approval from 20 days and under since receipt of eligible document as prescribed;

- Time for assessment and approval of the tasks and purpose zone construction planning project:

+ For general planning of purpose zones, time for the assessment of the tasks is from 20 days and under, for approval from 15 days and under; time for assessment of the project is from 25 days and under, for approval from 15 days and under since receipt of eligible document as prescribed;

+ For zoning plan, detailed planning of purpose zones, time for assessment of the tasks is from 15 days and under, for approval from 10 days and under; time for assessment of the project is from 25 days and under, for approval from 15 days and under since receipt of eligible document as prescribed;

- Time for assessment and approval of the tasks and rural construction planning project

+ For general commune construction planning,  time for assessment of the tasks is from 15 days and under, for approval from 10 days and under; time for assessment of the project is from 20 days and under, for approval from 15 days and under since receipt of eligible document as prescribed;

+ For detailed construction planning of rural residential quarters, time for assessment of the tasks is from 15 days and under, for approval from 10 days and under; time for assessment of the project is from 25 days and under, for approval from 15 days and under since receipt of eligible document as prescribed;

>> CLICK HERE TO READ THIS ARTICLE IN VIETNAMESE

331 lượt xem



  • Address: 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City
    Phone: (028) 7302 2286
    E-mail: info@lawnet.vn
Parent company: THU VIEN PHAP LUAT Ltd.
Editorial Director: Mr. Bui Tuong Vu - Tel. 028 3935 2079
P.702A , Centre Point, 106 Nguyen Van Troi, Ward 8, Phu Nhuan District, HCM City;