This content is mentioned in Circular No. 23/2013/TT-BCT of the Ministry of Industry and Trade of Vietnam regulating the contents and order to formulate, appraise and approve the design of construction of nuclear power plant.
According to Article 7 of Circular No. 23/2013/TT-BCT of the Ministry of Industry and Trade of Vietnam, the design of nuclear power plant project is changed and adjusted when there are requirements for change or during the performance. it is required to change and adjust the design to ensure the safety and quality of works and investment performance of the project.
To be specific:
- In case of adjustment of design making the change of location, constructional plan, objectives and scale or exceeding the total approved investment of works, the investor shall submit the adjusted design to the investment decider for appraisal and approval;
- In case of adjustment of design making the change of technical design, the investor must report to the Ministry of Industry and Trade for consideration and decision;
- In case of change of design of working drawing without changing the approved technical design, the investor may modify the design;
- The changes compared with the approved construction design must be shown in the as-built drawing.
View details at Circular No. 23/2013/TT-BCT of the Ministry of Industry and Trade of Vietnam, effective from December 01, 2013.