This content is mentioned in Circular No. 23/2013/TT-BCT of the Ministry of Industry and Trade of Vietnam regulating the contents and order to formulate, appraise and approve the design of construction of nuclear power plant.

According to Article 7 of Circular No. 23/2013/TT-BCT of the Ministry of Industry and Trade of Vietnam, the design of nuclear power plant project is changed and adjusted when there are requirements for change or during the performance. it is required to change and adjust the design to ensure the safety and quality of works and investment performance of the project.

Xây nhà máy điện hạt nhân Ninh Thuận: Hơn 3.200 tỉ đồng tái định cư - Báo  Người lao động

To be specific:

- In case of adjustment of design making the change of location, constructional plan, objectives and scale or exceeding the total approved investment of works, the investor shall submit the adjusted design to the investment decider for appraisal and approval;

- In case of adjustment of design making the change of technical design, the investor must report to the Ministry of Industry and Trade for consideration and decision;

- In case of change of design of working drawing without changing the approved technical design, the investor may modify the design;

- The changes compared with the approved construction design must be shown in the as-built drawing.

View details at Circular No. 23/2013/TT-BCT of the Ministry of Industry and Trade of Vietnam, effective from December 01, 2013.

Thu Ba

>> CLICK HERE TO READ THIS ARTICLE IN VIETNAMESE

23 lượt xem



  • Address: 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City
    Phone: (028) 7302 2286
    E-mail: info@lawnet.vn
Parent company: THU VIEN PHAP LUAT Ltd.
Editorial Director: Mr. Bui Tuong Vu - Tel. 028 3935 2079
P.702A , Centre Point, 106 Nguyen Van Troi, Ward 8, Phu Nhuan District, HCM City;