Acceptance of construction project products upon completion

This content is specifically guided in Circular 09/2016/TT-BXD which was issued by the Ministry of Construction on March 10, 2016.

Acceptance of completed work products is guided by Circular 09 as follows:

- The party awarding the contract will only accept the products of the contract when these products meet the quality requirements as stipulated.- The basis for product acceptance of the contract includes design drawings (including approved modifications and supplements by the contracting party); technical descriptions; relevant standards and regulations; test result certificates; acceptance handover documents and other related regulations.- The personnel involved in the acceptance and handover include: a representative of the awarding party, a representative of the contracting party, and a representative of the consultant (if any).- The acceptance and handover dossier includes:

- Minutes of acceptance for quality and completed quantity which are mutually agreed upon by the parties based on state regulations.- Test results of materials, products to be accepted, and other related regulations.

See details Circular 09/2016/TT-BXD effective from May 1, 2016.

- Thao Uyen -

>> CLICK HERE TO READ THIS ARTICLE IN VIETNAMESE

0 lượt xem



  • Address: 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City
    Phone: (028) 7302 2286
    E-mail: info@lawnet.vn
Parent company: THU VIEN PHAP LUAT Ltd.
Editorial Director: Mr. Bui Tuong Vu - Tel. 028 3935 2079
P.702A , Centre Point, 106 Nguyen Van Troi, Ward 8, Phu Nhuan District, HCM City;