The responsibility of the project owner pertaining to the approved EIA report in Vietnam

What are the current regulations on the responsibility of the project owner pertaining to the approved EIA report in Vietnam? Please get back to me.

The responsibility of the project owner pertaining to the approved EIA report in Vietnam (Image from the Internet)

Legal grounds:

- Clause 7, Article 1 of Decree 40/2019/ND-CP takes effect from July 1, 2019.

- Article 16 of Decree 18/2015/ND-CP.

The responsibility of the project owner pertaining to the approved EIA report according to the latest regulations of current law is as follows:

- Gain perception of sufficient contents and requirements of the EIA report approval decision to the investment project, construction investment project.

- Cooperate with the People’s Committee of commune from which the consultations are sought, during the EIA report compilation, in posting publicly the EIA report approval decision at the head office of the People’s Committee of commune, except for the case of consultation exemption prescribed in Clause 3 Article 21 of the Law on Environment Protection.

- Strictly satisfy requirements prescribed in Article 26 and Article 27 of the Law on Environment Protection.

- During the construction stage of the project, if the project owner has any change prescribed in Clause 2 Article 26 of the Law on Environment Protection, it must send a written report to the EIA report approval authority and make such change only after receiving a decision on environmental approval in the following cases:

+ Construction projects of industrial park infrastructure with additional investment sectors of a kind of manufacturing possibly causing environment pollution under group III Appendix Iia Section I issued herewith;

+ Expansion of scale and increase of capacity; change of technology of the project of a kind of manufacturing possibly causing environment pollution prescribed in Appendix Iia Section I issued herewith not subject to re-compilation of EIA report prescribed in Clause 2 Article 15 hereof.

- File, approve and implement the plan for hydroelectric reservoir cleaning before filling if the project has construction work of storage ponds or reservoirs; the reservoirs shall be filled after the approving authority carries out an inspection and grant a written approval.

- With regard to cases prescribed in column 4 Appendix II of this Decree, the project owner must send a report on results of environment protection works serving the operation phase on the basis of approved EIA report and approval for amendment (if any) sent to the approving authority for verification and confirmation of finished project before putting the project into official operation. With regard to project of investment having multiple phases, the results of environment protection works serving the operation phase shall be reported according to every phase of the project.

- Send a report on amendments and only implement amendments related to scope, scale, capacity, production technology, environment protection works and measures of projects after receiving the written approval issued by the approving authority.

Above is the consulting content.

Related Posts
LawNet
What is the significance of March 3? What is the lunar calendar date for March 3, 2025?
LawNet
What are holidays of Vietnam in March 2025? Which days are employees in Vietnam entitled to days off?
LawNet
What is February 28? What is the lunar date of February 28, 2025?
LawNet
What is significance of February 26? What is February 26, 2025, on the lunar calendar?
LawNet
What is significance of February 21? What is the lunar date of February 21, 2025?
LawNet
What are samples of the 54th UPU Letter Writing Competition in 2025 in Vietnamese?
LawNet
What are wishes for Valentine's Day (February 14) for girlfriend in Vietnamese?
LawNet
What are wishes on the Day of the God of Wealth 2025 for customers and partners in Vietnamese?
LawNet
What is February 16? What is February 16, 2025, on the lunar calendar?
LawNet
What is the date of Lantern Festival in 2025? Is Lantern Festival a public holiday where employees in Vietnam receive paid leave?
Lượt xem: 0
Latest Post

Đơn vị chủ quản: Công ty THƯ VIỆN PHÁP LUẬT.
Chịu trách nhiệm chính: Ông Bùi Tường Vũ - Số điện thoại liên hệ: 028 3935 2079
P.702A , Centre Point, 106 Nguyễn Văn Trỗi, P.8, Q. Phú Nhuận, TP. HCM;