Pursuant to Form No. 02, Appendix II, forms of dossiers of request for bonus payment promulgated together with Decree 15/2023/ND-CP stipulating the form of request for consideration of contract bonuses for construction contract packages of transport projects in 2023 are as follows:

 

CONTRACTOR
-------

SOCIALIST REPUBLIC OF VIETNAM
Independence - Freedom - Happiness
---------------

Number: ……

..., day month Year ...

 PROPOSAL FOR CONTRACT BONUS

To: (Investor)

Name of project, work: ……………………. Investment project code: ……………..

Name of the contract: ………….

Contractor's name: ……………………

Pursuant to the Government's Decree No. 15/2023/ND-CP dated April 25, 2023, stipulating the pilot contract award for construction and installation bidding packages belonging to traffic projects in the Program on economic recovery and development of socio-economic;

Pursuant to Contract No. ... date ... month ... ..., Contract Appendix No ... date ... month ... year ...;

Based on the minutes of acceptance, handover number ... date ... month ... year ...;

The contractor (name of contractor) ... requests (investor) to consider and award the construction and installation contract with the following contents:

Amount proposed for bonus (rounded, in million VND): ……………..

The calculation is as follows:

- Balance after bidding (TD): …………

- Actual time of implementation of the bidding package (date): …………

- Time to perform the bidding package under the contract (date): …………..

- Ratio of shortening time (TG): ………….

- Bonus amount (calculation): …………..

(Contractor) commits to have implemented the bidding package in accordance with the law on construction investment and according to the contract and contract appendix signed with the investor (with the minutes of acceptance and handover attached). 

(Contractor) proposes (investor) to consider, decide and carry out the procedures for the contractor to be awarded the contract according to regulations.

(The Contractor) would like to commit to the accuracy of information and data and will fully refund the adjustment and withdrawal amount as prescribed (with attached commitment).

 

 

CONTRACTOR
(Signature, full name, position and stamp)

 

What are principles for payment of contract bonuses for construction contract packages of transport projects in Vietnam in 2023?

According to Article 3 of Decree 15/2023/ND-CP stipulating principles for payment of contract bonuses for construction contract packages of transport projects as follows:

1. Works and work items shall be built in accordance with the contract (in terms of quantity, volume and quality), be built according to technical regulations and standards, and be accepted and handed over according to regulations of law on construction.

2. The payment of contract bonuses shall be public, transparent and fair; it shall be clearly stated in bidding documents, requests for proposals and contracts signed between investors and contractors.

3. The payment of contract bonuses shall be applied to each contract package.  The bonus shall not exceed unused fund after bidding specified in Article 4 of this Decree.

4. Contract bonuses shall be only paid to contractors who comply with the law when executing contract packages and there is an actual bonus fund.

5. Contract bonuses shall not be paid in cases where the price of the contract package is defined, the bidding document or request for proposals is made and the contract is signed in contravention of law on construction in order to profiteer from such bonuses.

Accordingly, the awarding of contracts for construction and installation bidding packages of traffic projects is carried out based on the following principles:

- Works and work items shall be built in accordance with the contract (in terms of quantity, volume and quality), be built according to technical regulations and standards, and be accepted and handed over according to regulations of law on construction.

- The payment of contract bonuses shall be public, transparent and fair; it shall be clearly stated in bidding documents, requests for proposals and contracts signed between investors and contractors.

- The contract bonus is applied to each specific bidding package. The amount of the bonus does not exceed the source of the bonus.

- The payment of contract bonuses shall be applied to each contract package.  The bonus shall not exceed unused fund after bidding.

- Contract bonuses shall be only paid to contractors who comply with the law when executing contract packages and there is an actual bonus fund.

- Contract bonuses shall not be paid in cases where the price of the contract package is defined, the bidding document or request for proposals is made and the contract is signed in contravention of law on construction in order to profiteer from such bonuses.

What are procedures for contract bonuses of construction contract packages of transport projects in Vietnam?

In Article 7 of Decree 15/2023/ND-CP stipulating procedures for contract bonuses of construction contract packages of transport projects as follows:

1. After the contract is accepted and handed over according to regulations, the contractor shall submit 05 applications for contract bonuses to the investor in person or by post (the duration of submission of such applications shall not exceed the deadline for work warranty). An application includes the original of the written request for contract bonuses (Form No. 02, Appendix II), the original of the written commitment to repay any or all of bonuses in case of adjustment or withdrawal of such bonuses (Form 03, Appendix II), copy of contract/contract appendix signed between the investor and the contractor with clause on contract bonuses, copies of records of acceptance or handover, copies of documents on work warranty and other documents under the contract as the basis for payment of contract bonuses (if any).

2. The investor shall receive applications at the request of the contractor according to regulations in Clause 1 of this Article.  If these applications are invalid, within 03 working days from the date of receipt of these applications, the investor shall give written notification and request the contractor to supplement such applications.

3. If these application are valid, the investor shall consider and decide payment of contract bonuses to the contractor within 30 days after receiving such valid applications. Decision on payment of contract bonuses shall clearly state contractor's name, name of contract package, the reduced time, bonuses, payment method, and expected time of payment and requirements for withdrawal of bonuses in case of adjustment of bonuses or occurrence of violations against rules for payment of contract bonuses (Form No. 04, Appendix II).

According to this Article, the procedures for contract bonuses of construction contract packages of transport projects include the following steps:

Step 1:

After the contract is checked, accepted and handed over according to regulations, the contractor sends directly or via postal service to the investor 05 sets of dossiers of request for contract bonuses (the time of submission of dossiers shall not exceed the deadline for closing the contract).

Step 2: The investor receives the dossier at the request of the contractor.

- In case the dossier is not valid, within 03 working days after receiving the dossier, the investor shall notify in writing and request the contractor to supplement the dossier for contract bonuses.

- In case the dossier is valid, the investor shall consider and decide to award the contract to the contractor within 30 days from the date of receipt of the valid dossier.

Best Regards!

Related Posts
LawNet
Vietnam: What is the driving license form from March 1, 2025? What information does the driving license contain?
LawNet
Vietnam issues Circular 12/2025/TT-BCA regarding driver examination; issuance and use of international driving permits
LawNet
Which province does vehicle plate number 37 belong to? What is the detailed license plates of Nghe An province in 2025?
LawNet
From March 01, 2025, shall persons failing the theoretical test continue to take the remaining parts of the exam for driving license in Vietnam?
LawNet
Which province in Vietnam has the license plate number 36? What documents must drivers carry when participating in road traffic in Vietnam?
LawNet
Which province in Vietnam has the license plate number 35?
LawNet
Which province in Vietnam has the license plate number 34?
LawNet
Which province in Vietnam has license plate number 33? What does the dossier for registration and issuance of auction-winning license plates in Vietnam include?
LawNet
Which province in Vietnam has the license plate number 32?
LawNet
Which province in Vietnam has license plate 31? Who is issued the license plate with red letters in Vietnam?
Lượt xem: 0
Latest Post

Đơn vị chủ quản: Công ty THƯ VIỆN PHÁP LUẬT.
Chịu trách nhiệm chính: Ông Bùi Tường Vũ - Số điện thoại liên hệ: 028 3935 2079
P.702A , Centre Point, 106 Nguyễn Văn Trỗi, P.8, Q. Phú Nhuận, TP. HCM;