What are regulations on producing the construction design and making the cost estimate for projects of dredging operations of marine navigation channels in Vietnam?

I'm studying about regulations on dredging of public marine navigation channels and inland navigation channels. What are regulations on producing the construction design and making the cost estimate for projects of dredging operations of marine navigation channels in Vietnam? Thank you!

Pursuant to Clause 1 Article 16 of the Decree 159/2018/NĐ-CP stipulating regulations on producing the construction design and making the cost estimate for projects of dredging operations of marine navigation channels in Vietnam as follows:

- Construction design and cost estimate shall be made on the basis of the topographic map giving a notice of depths of marine navigation channels and inland navigation channel which is latest, but less than 06 months till the design approval date; in case where the marine notice or the notice of inland navigation channels has been issued for more than 6 months before the design approval date, or data of these notices are not available, a survey must be conducted to create the construction design and cost estimate. The dredging volume specified in the design includes the alluvial soil volume estimated from the date of the measurement survey giving the marine and national inland waterway notice to the date of the measurement survey for handover of the cleared site; the step in formulating the project or economic-technical report and the step in evaluating and inspecting acceptance testing activities of the specialized construction body shall not be performed;

- As for the turnkey standard maintenance dredging carried out during the definite period and the irregular maintenance dredging carried out for the purpose of maintaining traffic safety, the Ministry of Transport shall provide detailed instructions for making the project design and cost estimate.

Above are regulations on producing the construction design and making the cost estimate for projects of dredging operations of marine navigation channels in Vietnam.

Best regards!

Related Posts
LawNet
Vietnam: What is the driving license form from March 1, 2025? What information does the driving license contain?
LawNet
Vietnam issues Circular 12/2025/TT-BCA regarding driver examination; issuance and use of international driving permits
LawNet
Which province does vehicle plate number 37 belong to? What is the detailed license plates of Nghe An province in 2025?
LawNet
From March 01, 2025, shall persons failing the theoretical test continue to take the remaining parts of the exam for driving license in Vietnam?
LawNet
Which province in Vietnam has the license plate number 36? What documents must drivers carry when participating in road traffic in Vietnam?
LawNet
Which province in Vietnam has the license plate number 35?
LawNet
Which province in Vietnam has the license plate number 34?
LawNet
Which province in Vietnam has license plate number 33? What does the dossier for registration and issuance of auction-winning license plates in Vietnam include?
LawNet
Which province in Vietnam has the license plate number 32?
LawNet
Which province in Vietnam has license plate 31? Who is issued the license plate with red letters in Vietnam?
Lượt xem: 0
Latest Post

Đơn vị chủ quản: Công ty THƯ VIỆN PHÁP LUẬT.
Chịu trách nhiệm chính: Ông Bùi Tường Vũ - Số điện thoại liên hệ: 028 3935 2079
P.702A , Centre Point, 106 Nguyễn Văn Trỗi, P.8, Q. Phú Nhuận, TP. HCM;