The criteria for acceptance testing of performance of national railway management and maintenance operations in Vietnam

What are the criteria for acceptance testing of performance of national railway management and maintenance operations in Vietnam? Please get back to me.

(hung**@gmail.com)

Article 9, Circular 06/2019/TT-BGTVT regulating the criteria for surveillance and acceptance testing of maintenance performance of national railway infrastructure in terms of maintenance quality, regime and procedures issued by the Minister of Transport (effective from April 1, 2019) stipulates criteria for acceptance testing of performance of national railway management and maintenance operations as follows:

1. Acceptance testing of compliance with the maintenance processes and plans for costing of public products and services in the railway infrastructure maintenance sector which have already been approved, applied standards, technical regulations, regulations on management and usage of building materials, engineering indications (if any), contracts already in effect and other relevant regulations regarding management of quality of construction works.

2. The quality of railway infrastructure after maintenance must conform to technical requirements set out in Article 5 herein.

3. Implementation of tasks of preparation, update and archival of documentation on management of national railway infrastructure assets; documents and records on regular and periodic monitoring and inspection; documents and records on monitoring of locations causing impacts on the traffic safety for the purpose of giving updates on these locations in systems for overall management and monitoring of railway infrastructure in accordance with regulations in force.

4. Criteria for assessment of acceptance testing results:

a) The after-maintenance quality of national railway infrastructure assets shall be assessed at two levels, including “pass” and “fail”;

b) A railway infrastructure asset will be ranked "pass” if preparation, update and archival of documents and records are ranked "pass" and all of maintenance operations after the initial acceptance testing or the acceptance re-testing are assessed as "pass";

c) A railway infrastructure asset will be ranked "fail” if preparation, update and archival of documents and records are ranked "fail" and at least one maintenance operation after the initial acceptance testing or the acceptance re-testing is assessed as "fail";

d) Contents and methods of assessment of the quality of implementation of tasks of management and maintenance of railway infrastructure assets shall be subject to provisions laid down in Appendices 1, 2, 3, 4, 5 and 6 herein.

For your information.

Best regards!

Related Posts
LawNet
What are penalties for failing to comply with the commands of Traffic Police of Vietnam?
LawNet
Is it mandatory to notarize and authenticate the written agreement on motorcycle sale in Vietnam?
LawNet
What age is eligible to take the driving test for B1 class driving licenses in Vietnam?
LawNet
Vietnam: Can a 25-year-old person take the driving test for a driving license to operate 16-seat passenger motor vehicles?
LawNet
Regulations on permissible fire prevention and fighting height and fire compartment area for residential buildings in Vietnam
LawNet
Are mobile police cars in Vietnam eligible for road use fee exemption?
LawNet
Is bringing toy guns on an airplane allowed in Vietnam?
LawNet
Is an appointment letter for issuance of driving license valid as driving license in Vietnam?
LawNet
Vietnam: Is it possible to take the Class C driver license test if the Class B2 license is still valid?
LawNet
How much is the fine for operating a car without brake lamps in Vietnam according to Decree 100?
Lượt xem: 0
Latest Post

Đơn vị chủ quản: Công ty THƯ VIỆN PHÁP LUẬT.
Chịu trách nhiệm chính: Ông Bùi Tường Vũ - Số điện thoại liên hệ: 028 3935 2079
P.702A , Centre Point, 106 Nguyễn Văn Trỗi, P.8, Q. Phú Nhuận, TP. HCM;