Report Content to the Civil Aviation Authority on the Implementation of Airport Planning
According to Clause 2, Article 1 of Circular 30/2020/TT-BGTVT (Effective from January 15, 2021) amending Circular 17/2016/TT-BGTVT, this content is stipulated as follows:
- Name of the report: Report on the implementation status of airport master plans;
- Content of the report: The contents related to the implementation status of airport master plans as stipulated in Form No. 15 of the Appendix issued together with this Circular;
- Method of sending and receiving the report: The report can be in the form of paper documents or electronic documents. The report is sent to the receiving agency by one of the following methods: direct submission, via postal service, fax, via the email system, or other methods as regulated by law;
- Frequency of reporting: Annually;
- Deadline for submitting the report: Before December 18 each year;
- Reporting data cut-off time: From December 15 of the year preceding the reporting period to December 14 of the reporting period;
- Report outline template: According to the regulations in Form No. 15 of the Appendix issued together with this Circular.
Above is the content regarding the report to the Civil Aviation Authority on the implementation status of airport master plans.