Procedures for allocation of land at airports and aerodromes according to new regulations in Vietnam

Has there been a document amending Circular 17/2016/TT-BGTVT on the management and operation of airports and aerodromes in Vietnam? So what is implementation of procedures for allocation of land at airports and aerodromes according to new regulations in Vietnam?

According to Article 17 of Circular 17/2016/TT-BGTVT, as amended by Clause 3 of Article 1 of Circular 30/2020/TT-BGTVT, the content is regulated as follows:

1. An organization requiring land shall submit 01 application for land allocation to the relevant airports authority by hand, by post or by other methods. The application for land allocation includes:

a) The application form defined in Form No. 01 annexed to this Circular;

b) The copy of the certificate of business registration if the applicant is a company providing aviation or non-aviation services in the airport or aerodrome;

c) Copy from the original copy or copy produced together with the original copy for comparison or certified true copy (if the application is submitted in person), certified true copy (if the application is submitted by post) of the written approval for investment guidelines or decision on investment approval or investment registration certificate;

d) The extract of the cadastral map or the cadastral extract of the land parcel.

2. If the application is insufficient or invalid, the airports authority shall, in no more than 03 working days upon receiving such application, inform and guide the applicant to supplement and complete the documents as per regulations.

3. In no more than 05 working days upon receiving the valid application, the airports authority shall issue in writing an explained rejection or an approval of land allocation via Form No. 02 annexed to this Circular; deliver the land area on-site and make the allocation record via Form No. 04 annexed to this Circular.

4. In no more than 05 working days upon the approval of land allocation, the airports authority shall be responsible for sending the written approval, the extract of the cadastral map or the cadastral extract of the land parcel to the Civil Aviation Authority of Vietnam and the relevant land registry office to update and revise the cadastral archive and land database.

Above is the content about procedures for allocation of land at airports and aerodromes according to the new regulations.

Best Regards!

Related Posts
LawNet
Vietnam: What is camera violation?
LawNet
What is the size of a photo attached to the application form for issuance of seaman’s books in Vietnam?
LawNet
From January 1, 2025, what are places where vehicle operators in Vietnam are not allowed to stop, park?
LawNet
What is the license plate symbol of Thanh Hoa province?
LawNet
What is the license plate symbol for motor vehicles and motorcycles in Bac Ninh Province?
LawNet
What is the license plate symbol for motor vehicles and motorcycles in Ben Tre Province?
LawNet
What is the license plate symbol of Lam Dong province?
LawNet
What is the license plate symbol for motor vehicles and motorcycles in Bac Lieu Province?
LawNet
What is the license plate symbol of Dak Nong province?
LawNet
May fines for driving a car over the speed limit in Vietnam be paid many times?
Lượt xem: 0
Latest Post

Đơn vị chủ quản: Công ty THƯ VIỆN PHÁP LUẬT.
Chịu trách nhiệm chính: Ông Bùi Tường Vũ - Số điện thoại liên hệ: 028 3935 2079
P.702A , Centre Point, 106 Nguyễn Văn Trỗi, P.8, Q. Phú Nhuận, TP. HCM;