According to Clause 2, Article 4 of Circular 05/2024/TT-BKHDT, the following fee rates are specified:
Fee Rates
1. The cost of maintaining the name and capability profile of the contractor on the System shall be implemented in accordance with the provisions at point a, Clause 11, Article 12 of Decree 24/2024/ND-CP dated February 27, 2024, of the Government, which details certain articles and measures for the implementation of the Bidding Law regarding the selection of contractors (referred to as Decree 24/2024/ND-CP).
The cost of maintaining the name and capability profile of the investor on the System is 330,000 VND per year (including value-added tax). The investor shall pay this fee from the second year onwards after registration to participate in the System.
2. The cost of submitting bidding documents on the System shall be implemented in accordance with the provisions at point b, Clause 11, Article 12 of Decree 24/2024/ND-CP.
...
Pursuant to Clause 11.b Article 12 of the Decree 24/2024/ND-CP stipulating fees associated with contractor selection:
Fees associated with contractor selection
...
11. Fees for contractor selection on VNEPS include:
...
b) The fee for submission of bids on VNEPS is: 330,000 VND for 1 package (including value added tax) for competitive bidding, limited bidding, online quotation under ordinary procedures; 220,000 VND for 1 package (including value added tax) for shopping method;
...
As regulated above, the fee for submission of bids on Vietnam National E-Procurement System (VNEPS) in 2024 is as follows:
- 330,000 VND for 1 package (including value added tax) for competitive bidding, limited bidding, online quotation under ordinary procedures
- 220,000 VND for 1 package (including value added tax) for shopping method
What is the fee for submission of bids on Vietnam National E-Procurement System (VNEPS) in 2024? - image from internet
What are bid evaluation methods applied to consulting service packages in Vietnam?
Pursuant to Article 59 of the Law on Bidding in 2023 stipulating bid evaluation methods applied to consulting service packages:
- Least-cost method
- Fixed-price method
- Combined technique and price-based method
- Technique-based method
What are prohibited acts in bidding regarding bids in Vietnam?
Pursuant to Article 16 of the Law on Bidding in 2023 stipulating prohibited acts in bidding regarding bids in Vietnam:
- Reaching, with or without undue influence, an arrangement or agreement which is designed to let one or more parties to prepare bids for all bidders or to withdraw submitted bids so that one of them will win the bid;
- A bidder or investor with appropriate qualifications and experience has submitted a bid and meets the requirements laid down in the bidding documents but deliberately refuses to provide additional documents proving their capacity and experience at the procuring entity’s request for clarification of the bid or verification of their submitted documents with the aim of facilitating one party’s winning of the bid;
- Deliberately providing information and documents which are not accurate or objective in bids with the aim of falsifying the contractor/investor selection result;
- A person or entity concurrently engages in the evaluation of bids and the appraisal of the contractor or investor selection result of the same package or investment project;
- A bidder submits a bid for a procurement, construction or non-consulting service package for which the bidder is also acting as a consultant;
- Disclosing documents and information about the contents of the bids of the inviting party; clarifying the requirements for the bids of the contractor and investor during the evaluation process; documenting meeting minutes, opinions, evaluations of the bids before they are publicly disclosed according to regulations.
- Subcontracting in the case where: The contractor transfers to another contractor a portion of the work within the bidding package that does not exceed the maximum value allocated for subcontractors as stated in the contract, but beyond the scope of work proposed in the bids, the proposed dossier that has not been approved by the investor or supervisory consultant.