What are tasks and powers of the project management board in the use of aid in Vietnam?

What are tasks and powers of the project management board in the use of aid in Vietnam? What are regulations on modification and supplementation of program or project during the implementation process of the use of aid in Vietnam?  I would like to know some information related to the management and use of aid in Vietnam.

Tasks and powers of the project management board in the use of aid in Vietnam:

Pursuant to Article 15 of the Decree 80/2020/NĐ-CP stipulating tasks and powers of the project management board as follows:

1. Represent the project owner, be held accountable to the project owner, managing agency and take legal responsibility for their decisions.

2. The project management board must open accounts at the State Treasury system where transactions are made or commercial banks that are established and operate under Vietnamese law. Perform revenue and expenditure activities for the aid through accounts on the basis of the approved financial plan.

3. The project management board\ shall perform tasks within the project framework, including:

a) Make the overall and annual implementation plan, the financial plan of the project and submit it to the head of the managing agency for approval;

b) Negotiate and sign contracts;

c) Carry out bidding works and manage contracts within their assigned scope;

d) Manage finance and assets and carry out procedures for disbursement, accounting and settlement in accordance with the financial management regulations of this Decree and in accordance with provisions of the aid donor.

4. Formulate detailed plans to supervise and evaluate the implementation of program or project.

5. Report on the implementation of the program or project, every 6 months and every year, and financial management status to the project owner and the managing agency.

6. Carry out taking-over inspection, transfer and final accounts of program or project. After finishing the program or project, within 06 months, the project management board must complete the report on completion of the program or project and send it to the project owner.

7. Other duties assigned.

Regulations on modification and supplementation of program or project during the implementation process of the use of aid in Vietnam:

Pursuant to Article 16 of the Decree 80/2020/NĐ-CP stipulating modification and supplementation of program or project during the implementation process as follows: 

1. For programs or projects subject to approval of the Prime Minister:

The managing agency shall carry out the procedure to submit to the Prime Minister when there are any adjustments, modifications or additions that lead to changes in the contents of the aid approval decision.

2. For programs or projects subject to approval of the managing agencies:

a) Modifications or supplementations that will make a program or project fall into any of the cases specified in Clause 1 Article 7 of this Decree must be submitted to the Prime Minister for consideration and approval;

b) Modifications or supplementation not mentioned at Point a Clause 1 of this Article shall be approved by approving agency.

3. Procedures shall conform to Articles 8, 10 and 11 of this Decree.

Best regards!

Related Posts
LawNet
Vietnam: Evaluation of pre-qualification applications for PPP projects applying the competitive bidding
LawNet
What are the regulations on contract conclusion and disclosure of information about the PPP project contract in Vietnam?
LawNet
Vietnam: What are the detailed procedures for applying the direct contracting method to select investors of PPP projects?
LawNet
What are the regulations on document retention in PPP investment in Vietnam?
LawNet
What are regulations on educational activities in primary schools in Vietnam?
LawNet
What are the methods of wind monitoring in Vietnam?
LawNet
Is it permissible to applying the shortened process of shopping for package of procurement of commonly used goods in Vietnam?
LawNet
What are details of proposal for approval of the result of evaluation of E-HSDXKT with regard to a package adopting single-stage two-envelope procedure in Vietnam?
LawNet
What is the newest form used to make decision on approval of the contractor selection plan in Vietnam in 2024?
LawNet
What are conditions for issuing bidding documents used for investor selection in Vietnam?
Lượt xem: 0
Latest Post

Đơn vị chủ quản: Công ty THƯ VIỆN PHÁP LUẬT.
Chịu trách nhiệm chính: Ông Bùi Tường Vũ - Số điện thoại liên hệ: 028 3935 2079
P.702A , Centre Point, 106 Nguyễn Văn Trỗi, P.8, Q. Phú Nhuận, TP. HCM;