08:18 | 08/03/2023

What are regulations on payment of advances and recovery of advances regarding construction projects financed by public investments in Vietnam?

Hello Lawnet. I have a question. What are regulations on payment of advances and recovery of advances regarding construction projects financed by public investments in Vietnam? Thank you!

Pursuant to Article 6 of the Circular 107/2018/TT-BTC stipulating regulations on payment of advances and recovery of advances regarding construction projects financed by public investments in Vietnam as follows:

Payment of advances and recovery of advances for investment and construction projects of overseas Vietnamese bodies shall conform to regulations on payment of advances and recovery of advances on state budget-funded investments laid down in the Circulars of the Ministry of Finance such as Circular No. 08/2016/TT-BTC dated January 18, 2016, Circular No. 108/2016/TT-BTC dated June 30, 2016 and Circular No. 52/2018/TT-BTC dated May 24, 2018.

As regards construction contracts signed abroad, if they are executed under regulations of host countries and laws of Vietnam on payment of advances, recovery of advances and contract advance guarantee, signed contracts must apply.

In specific cases where projects of particular nature need advances greater than the prescribed limit, the State Treasury shall pay advances which do not exceed the limit of investments to be allocated to a project in a financial year upon the presiding ministry’s request.

In specific cases where projects of particular nature need advances even when documents evidencing advances prescribed herein are not sufficient in accordance with regulations of host countries, the presiding ministry must send explanatory documents to the Ministry of Finance to request its review and grant of its decision.

In this case, the presiding ministry shall send the written request for advances on investments specific to project items (specifying monetary amount, accounts and beneficiaries). The written request for payment of investments made by the presiding ministry shall be subject to the Appendix No.05 hereto.

Above are regulations on payment of advances and recovery of advances regarding construction projects financed by public investments in Vietnam.

Best regards!

Related Posts
LawNet
What is a digital signature certificate? What are regulations on classification of digital signature certificates in Vietnam?
LawNet
List of templates of documents related to special investment procedures in 2025 in Vietnam
LawNet
What is the template of the Report on the results of construction design appraisal in 2025 in Vietnam?
LawNet
What is PPP project contract in Vietnam? What are the types of PPP project contracts in Vietnam?
LawNet
What is a PPP project? Which PPP projects are classified according to the authority for investment policy decision in Vietnam?
LawNet
Which packages shall be applied for selection of contractors in special cases in Vietnam?
LawNet
What is bidding in advance according to the law in Vietnam? Which packages can be subjected to bidding in advance in Vietnam?
LawNet
What are forms and methods for selecting investors in Vietnam in 2025?
LawNet
List of business lines and business establishments encouraged to invest in or relocate to industrial clusters in Vietnam
LawNet
What is the template of the Appraisal Report of Construction Design Following Basic Design in Vietnam according to Decree 175?
Lượt xem: 0
Latest Post

Đơn vị chủ quản: Công ty THƯ VIỆN PHÁP LUẬT.
Chịu trách nhiệm chính: Ông Bùi Tường Vũ - Số điện thoại liên hệ: 028 3935 2079
P.702A , Centre Point, 106 Nguyễn Văn Trỗi, P.8, Q. Phú Nhuận, TP. HCM;