Procedures for Selecting Contractors in Construction Activities Using Public Investment Capital within the People's Court System

Sequence for selecting contractors in construction activities for projects using public investment capital under the People's Court system? How is the authority to approve the contractor selection plan for non-decentralized projects using public investment capital under the People's Court system delegated?

Procedure for Selecting Contractors in Construction Activities for Projects Using Public Investment Funds within the People's Court System

Pursuant to Article 14 of the Regulation on Certain Contents of Investment Construction Project Management Using Public Investment Funds within the People's Court System, issued in conjunction with Decision 608/QD-TANDTC-KHTC in 2021 by the Chief Justice of the Supreme People's Court, the procedure for selecting contractors in construction activities is stipulated as follows:

  1. Preparing, Appraising, and Approving the Contractor Selection Plan

a) Based on the approved total estimate, the investor organizes the preparation of the contractor selection plan in accordance with the Law on Bidding and related legal documents, and submits it to the Investment Decision Maker for approval.

b) The division of the project into bidding packages must be based on technical characteristics and implementation sequence; ensure project synchronization and reasonable package scale. It is strictly prohibited to divide packages with the intent of direct appointment or to limit the participation of contractors.

c) The Investment Decision Maker organizes the appraisal and approval of the contractor selection plan, except for the contractor selection plan in the investment preparation stage.

  1. Organizing Contractor Selection

a) Based on the approved contractor selection plan, the investor organizes the selection of contractors according to the contents specified in the contractor selection plan, including: Name of the package; Package price; Source of capital; Form of contractor selection; Method of contractor selection; Time to start organizing contractor selection; Type of contract; Contract implementation time.

b) Any changes or adjustments to the contents in the contractor selection plan must be approved by the Investment Decision Maker, except for the package price content specified in Clause 2, Article 117, Decree 63/2014/ND-CP.

Authorization to Approve the Contractor Selection Plan for Non-decentralized Projects Using Public Investment Funds within the People's Court System

According to Article 15 of the Regulation on Certain Contents of Investment Construction Project Management Using Public Investment Funds within the People's Court System, issued in conjunction with Decision 608/QD-TANDTC-KHTC in 2021 by the Chief Justice of the Supreme People's Court regarding the authorization to approve the contractor selection plan for non-decentralized projects as follows:

The Chief Justice of the Supreme People's Court authorizes the Chief Justices of the Provincial People's Courts to approve, approve adjustments, and supplement the contractor selection plan for the packages that serve for the design implementation after the basic design.

Respectfully!

Related Posts
LawNet
What is a digital signature certificate? What are regulations on classification of digital signature certificates in Vietnam?
LawNet
List of templates of documents related to special investment procedures in 2025 in Vietnam
LawNet
What is the template of the Report on the results of construction design appraisal in 2025 in Vietnam?
LawNet
What is PPP project contract in Vietnam? What are the types of PPP project contracts in Vietnam?
LawNet
What is a PPP project? Which PPP projects are classified according to the authority for investment policy decision in Vietnam?
LawNet
Which packages shall be applied for selection of contractors in special cases in Vietnam?
LawNet
What is bidding in advance according to the law in Vietnam? Which packages can be subjected to bidding in advance in Vietnam?
LawNet
What are forms and methods for selecting investors in Vietnam in 2025?
LawNet
List of business lines and business establishments encouraged to invest in or relocate to industrial clusters in Vietnam
LawNet
What is the template of the Appraisal Report of Construction Design Following Basic Design in Vietnam according to Decree 175?
Lượt xem: 0
Latest Post

Đơn vị chủ quản: Công ty THƯ VIỆN PHÁP LUẬT.
Chịu trách nhiệm chính: Ông Bùi Tường Vũ - Số điện thoại liên hệ: 028 3935 2079
P.702A , Centre Point, 106 Nguyễn Văn Trỗi, P.8, Q. Phú Nhuận, TP. HCM;