What is the duration for preparation of bid or proposal for domestic competitive bidding in Vietnam?

What is the duration for preparation of bid or proposal for domestic competitive bidding in Vietnam? Is the number of bidders participating in competitive bidding limited in Vietnam?

What is the duration for preparation of bid or proposal for domestic competitive bidding in Vietnam?

According to Article 45 of the Bidding Law 2023 stipulating the contractor selection duration in Vietnam:

Article 45. Contractor selection duration

1. The Contractor selection duration is stipulated as follows:

a) The preparation time for interest registration documents and prequalification documents is at least 09 days for domestic bidding and 18 days for international bidding from the first day the interest invitation documents and prequalification invitation documents are issued to the deadline for bid closing;

b) The preparation time for bidding documents for competitive bidding and limited bidding is at least 18 days for domestic bidding and 35 days for international bidding from the first day the bidding invitation documents are issued to the deadline for bid closing; for construction, mixed packages with a package value not exceeding VND 20 billion, and goods and non-consulting service procurement packages with a package value not exceeding VND 10 billion, the preparation time for bidding documents is at least 09 days for domestic bidding and 18 days for international bidding;

c) The preparation time for bidding documents for competitive offering is at least 05 working days from the first day the bidding invitation documents are issued to the deadline for bid closing;

[...]

Thus, the duaration of preparation of bid or proposal for domestic competitive bidding is 18 days from the first day the bidding invitation documents are issued to the deadline for bid closing.

What    is    the    preparation    time    for    bidding    documents    for    domestic    open    bidding?

What is the duration for preparation of bid or proposal for domestic competitive bidding in Vietnam? (Internet image)

Is the number of bidders participating in competitive bidding limited in Vietnam?

According to Article 21 of the Bidding Law 2023 stipulating competitive bidding in Vietnam:

Article 21. Competitive bidding

  1. Competitive bidding is a form of contractor selection without limiting the number of participating contractors.

  2. Competitive bidding applies to all packages, except for cases prescribed in Articles 22, 23, 24, 25, 26, 27, 28, and 29 of this Law. If competitive bidding is not implemented, the document requesting approval of the contractor selection plan must clearly state the reasons for not conducting competitive bidding; the authorized person decides and takes responsibility for not applying competitive bidding.

According to the above regulation, competitive bidding is a form of contractor selection without limiting the number of participating contractors.

Which methods of contractor selection are applied in competitive bidding?

According to Article 30 of the Bidding Law 2023 stipulating the single-stage one-envelope procedure in Vietnam:

Article 30. Single-stage one-envelope procedure

1. The one-stage one-envelope method is applied in the following cases:

a) competitive bidding, limited bidding for the procurement of non-consulting services, goods, construction, and mixed packages, except for the case specified at point b clause 1 Article 31 of this Law;

b) Competitive offering for the procurement of non-consulting services, goods, construction, and mixed goods and construction packages;

c) Direct contracting for the procurement of consulting services, non-consulting services, goods, construction, and mixed packages;

d) Direct procurement for goods procurement packages.

[...]

According to Article 31 of the Bidding Law 2023 stipulating the single-stage two-envelope procedure in Vietnam:

Article 31. Single-stage two-envelope procedure

  1. The one-stage two-envelope method is applied in the following cases:

a) competitive bidding, limited bidding for consultancy service packages;

b) competitive bidding, limited bidding for non-consulting service, goods procurement, construction, and mixed packages that require high technical requirements as prescribed by the law on science and technology.

[...]

According to Article 32 of the Bidding Law 2023 stipulating the two-stage one-envelope procedure:

Article 32. Two-stage one-envelope procedure

  1. The two-stage one-envelope procedure is applied in cases of competitive bidding, limited bidding for goods procurement, construction, and mixed packages where the specific, complete technical requirements for the package cannot be precisely determined at the time of bidding organization.

[...]

According to Article 33 of the Bidding Law 2023 stipulating the two-stage two-envelope procedure:

Article 33. Two-stage two-envelope procedure

  1. The two-stage two-envelope procedure is applied in cases of competitive bidding, limited bidding for goods procurement, construction, and mixed packages with new, complex technologies or specific characteristics where the specific, complete technical requirements for the package cannot be precisely determined at the time of bidding organization.

[...]

According to the above regulation, competitive bidding can apply the following methods of contractor selection:

- Single-stage one-envelope procedure

- Single-stage two-envelope procedure

- Two-stage one-envelope procedure

- Two-stage two-envelope procedure

Related Posts
LawNet
Where to Apply for an Investment Registration Certificate When a Project is Implemented Both Inside and Outside the Industrial Park?
LawNet
Where Must a Company Apply for an Investment Registration Certificate?
LawNet
Does the Company Need to Apply for an Investment Registration Certificate?
LawNet
Principles for Payment of State's Capital Contribution in PPP Projects
LawNet
The State Capital Contribution in PPP Projects
LawNet
Investor Profits in the Implementation of PPP Projects
LawNet
Interest Rates for Mobilizing Investment Capital in Implementing PPP Projects
LawNet
Procedure for Upgrading Second-Class Construction Capacity Certificates
LawNet
Criteria for Determining the Investor's Equity in Implementing PPP Projects
LawNet
Content of the Financial Plan for the PPP Project
Lượt xem: 0
Latest Post

Đơn vị chủ quản: Công ty THƯ VIỆN PHÁP LUẬT.
Chịu trách nhiệm chính: Ông Bùi Tường Vũ - Số điện thoại liên hệ: 028 3935 2079
P.702A , Centre Point, 106 Nguyễn Văn Trỗi, P.8, Q. Phú Nhuận, TP. HCM;