Preparation, appraisal, and approval of online bidding documents following the single-stage two-envelope procedure in Vietnam
What are regulations on Preparation, appraisal, and approval of online bidding documents following the single-stage two-envelope procedure in Vietnam? Hello Lawnet, I am Quang Huy, currently living and working in Dong Nai. I am currently working at a company that supplies equipment to state agencies and public service units. My company regularly participates in bidding packages for the procurement of equipment for state agencies and public service units. I have heard about the national bidding network system. As far as I know, there will be new regulations on selecting contractors through the national bidding network system in the near future. So, according to the new regulations, what are regulations on Preparation, appraisal, and approval of online bidding documents following the single-stage two-envelope procedure in Vietnam? Which document regulates this issue? I hope the you will help me answer. Thank you.
Preparation, appraisal, and approval of online bidding documents following the single-stage two-envelope procedure in Vietnam
The Preparation, appraisal, and approval of online bidding documents following the single-stage two-envelope procedure in Vietnam are regulated in Article 25 of Circular 04/2017/TT-BKHDT, which specifies the details regarding the selection of contractors through the National Online Bidding System issued by the Minister of Planning and Investment of Vietnam (effective from March 1, 2018). To be specific:
-
The bidding party logs into the System, then selects the corresponding section “Goods” or “Construction” or “Non-consulting Services” to prepare the E-TBMT and other contents of the E-HSMT.
-
After preparing the E-HSMT, the bidding party prints the E-HSMT and submits it to the investor for evaluation and approval. The bidding party is responsible for ensuring the consistency between the E-HSMT content on the System and the E-HSMT approved by the investor.
-
In case it is necessary to amend the E-HSMT, the bidding party logs in and directly edits it on the System after obtaining approval from the investor regarding the content.
-
If there is a discrepancy between the information in the attached E-HSMT file issued by the bidding party on the System and the information in the webform, the information in the webform shall be the basis for preparing and evaluating the E-HSDT.
E-TBMT is the notice of bid invitation, the notice of quotation invitation for packages applying the selection of contractors through the network.
E-HSMT is the bid invitation document, the proposal document, the request for quotation for packages applying the selection of contractors through the network.
E-HSDT is the bidding document, the proposal document, the quotation for packages applying the selection of contractors through the network.
The above is advice on preparing, evaluating, and approving online bidding documents with a one-stage two-envelope method. For more detailed information, you should refer to Circular 04/2017/TT-BKHDT. We hope our advice will be helpful to you.
Detailed Online Contractor Selection Process in Vietnam
According to Article 24 of Circular 04/2017/TT-BKHDT, the detailed process is as follows:
1. Preparation for contractor selection, including:
a) Preparing the E-HSMT;
b) Evaluating and approving the E-HSMT.
2. Organizing contractor selection, including:
a) Announcing the invitation to bid and issuing the E-HSMT;
b) Amending and clarifying the E-HSMT;
c) Submitting the E-HSDT;
d) Opening the E-HSĐXKT.
3. Evaluating the E-HSĐXKT, submitting, evaluating, and approving the list of contractors meeting technical requirements.
4. Opening the E-HSĐXTC.
5. Evaluating the E-HSĐXTC and ranking contractors.
6. Negotiating the contract, submitting, evaluating, approving, and disclosing the results of the contractor selection.
7. Completing and signing the contract.