11:23 | 05/09/2024

Minor Repairs Under VND 50 Million by the Commune People's Committee: Are Project Assessments Required?

For small repair projects under 50 million VND, can the Commune People's Committee (UBND) carry out the appraisal by itself?

According to Clause 2, Article 5 of Decree 59/2015/ND-CP, an investment project for construction works only requires the preparation of an Economic-Technical Construction Investment Report if it includes:

- Construction works used for religious purposes;

- New construction, repair, renovation, or upgrading works with a total investment of less than 15 billion VND (excluding land levy).

Therefore, the commune People's Committee's repair project with a scale of 50 million VND, if excluding the land levy, is considered an investment project for construction works that only requires the preparation of an Economic-Technical Construction Investment Report.

Furthermore, under Clause 5, Article 57 of the Construction Law 2014, it is stipulated that for an investment project for construction works that only requires an Economic-Technical Construction Investment Report, the authority to appraise the project is specified as follows:

- In cases where state budget funds are used, the specialized construction agency is responsible for leading the appraisal of the contents of the Economic-Technical Construction Investment Report as specified in Clause 4, Article 58 of the Construction Law 2014;

- In cases where state funds outside the budget are used, the specialized construction agency according to the decentralization is responsible for leading the appraisal of the construction drawing design and construction estimates. The specialized agency under the investment decision-maker will appraise the technological design (if any) and other contents of the Economic-Technical Construction Investment Report;

- In cases where other types of funds are used, the investment decision-maker or the project owner organizes the appraisal of the construction drawing design and construction estimates by themselves, except for special-grade, grade I structures, and works that significantly affect the landscape, environment, and community safety, and takes responsibility for the appraisal contents.

Therefore, the 50 million VND repair project of the commune People's Committee must carry out the appraisal of the construction investment project as stipulated above.

Sincerely!

Related Posts
LawNet
Where to Apply for an Investment Registration Certificate When a Project is Implemented Both Inside and Outside the Industrial Park?
LawNet
Where Must a Company Apply for an Investment Registration Certificate?
LawNet
Does the Company Need to Apply for an Investment Registration Certificate?
LawNet
Principles for Payment of State's Capital Contribution in PPP Projects
LawNet
The State Capital Contribution in PPP Projects
LawNet
Investor Profits in the Implementation of PPP Projects
LawNet
Interest Rates for Mobilizing Investment Capital in Implementing PPP Projects
LawNet
Procedure for Upgrading Second-Class Construction Capacity Certificates
LawNet
Criteria for Determining the Investor's Equity in Implementing PPP Projects
LawNet
Content of the Financial Plan for the PPP Project
Lượt xem: 0
Latest Post

Đơn vị chủ quản: Công ty THƯ VIỆN PHÁP LUẬT.
Chịu trách nhiệm chính: Ông Bùi Tường Vũ - Số điện thoại liên hệ: 028 3935 2079
P.702A , Centre Point, 106 Nguyễn Văn Trỗi, P.8, Q. Phú Nhuận, TP. HCM;