Is It Possible to Directly Appoint the Contractor Who Won the Most Recent Bid for the Same Project?

I represent the agency in selecting a contractor to upgrade the internal management software of the agency. Therefore, should I organize a tender or appoint the contractor who supplied the software last time? I look forward to the editorial board's support.

According to Clause 1, Article 22 of the 2013 Law on Bidding, regulations on contractor appointment are as follows:

- The bidding package that needs to be implemented immediately to remedy or promptly handle the consequences caused by force majeure; the bidding package that needs to be implemented to ensure state secrecy; the bidding package that needs to be implemented immediately to avoid direct harm to the life, health, and property of the community in the area or to avoid serious impact on adjacent constructions; the bidding package for purchasing drugs, chemicals, supplies, and medical equipment to carry out urgent epidemic prevention and control work;

- The urgent bidding package that needs to be implemented to protect national sovereignty, national borders, and islands;

- The bidding package for providing consulting services, non-consulting services, and procurement of goods that must be purchased from the previously performed contractor to ensure compatibility in technology, copyright that cannot be purchased from another contractor; the bidding package of a research and experimental nature; purchase of intellectual property rights;

- The bidding package for providing consulting services to prepare feasibility study reports, construction designs that are appointed to the author of the winning architectural design or selected design when the author meets the capacity conditions as prescribed; the bidding package for constructing monuments, reliefs, large-scale paintings, artworks linked with copyright from creation to construction;

- The bidding package for relocating technical infrastructure works directly managed by a specialized unit to serve the land clearance work; the bidding package for demining, and clearing explosive materials to prepare construction land;

- The bidding package for providing public products and services, the bidding package with a package price within the limit applicable for contractor appointment as stipulated by the Government of Vietnam in accordance with socio-economic conditions in each period.

=> Thus, to ensure compatibility with previously provided software, you can appoint the bidder who supplied that software.

The editorial board informs you.

Related Posts
LawNet
What is a digital signature certificate? What are regulations on classification of digital signature certificates in Vietnam?
LawNet
List of templates of documents related to special investment procedures in 2025 in Vietnam
LawNet
What is the template of the Report on the results of construction design appraisal in 2025 in Vietnam?
LawNet
What is PPP project contract in Vietnam? What are the types of PPP project contracts in Vietnam?
LawNet
What is a PPP project? Which PPP projects are classified according to the authority for investment policy decision in Vietnam?
LawNet
Which packages shall be applied for selection of contractors in special cases in Vietnam?
LawNet
What is bidding in advance according to the law in Vietnam? Which packages can be subjected to bidding in advance in Vietnam?
LawNet
What are forms and methods for selecting investors in Vietnam in 2025?
LawNet
List of business lines and business establishments encouraged to invest in or relocate to industrial clusters in Vietnam
LawNet
What is the template of the Appraisal Report of Construction Design Following Basic Design in Vietnam according to Decree 175?
Lượt xem: 0
Latest Post

Đơn vị chủ quản: Công ty THƯ VIỆN PHÁP LUẬT.
Chịu trách nhiệm chính: Ông Bùi Tường Vũ - Số điện thoại liên hệ: 028 3935 2079
P.702A , Centre Point, 106 Nguyễn Văn Trỗi, P.8, Q. Phú Nhuận, TP. HCM;