Bid evaluation rules for investment in airport service works in Vietnam

May I ask, according to the latest regulations, what do bid evaluation rules for investment in airport service works in Vietnam comprise?

What do bid evaluation rules for investment in airport service works in Vietnam comprise?

According to Article 23 of Circular 23/2021/TT-BGTVT, bid evaluation rules for investment in airport service works are as follows:

1. Bid evaluation must rely on bid evaluation criteria and other requirements under bidding documents, submitted bids, documents explaining and clarifying bids of investors in order to select investors with sufficient capacity and experience and sound technical, financial - commercial solutions to execute the projects.

2. Bid evaluation shall be carried out using photocopies, the consistency between which and the original copies must be guaranteed by investors. In case of any insignificant discrepancy between original copies and photocopies without altering ranking order of investors, the original copies shall prevail. In case of any significant discrepancy between original copies and photocopies which leads to difference between evaluation results based on original copies and those based on photocopies which alters ranking order of investors, bids of the investors will be eliminated.

3. Upon carrying out bid evaluation, procuring entities must inspect technical, financial - commercial aspects of bids in order to eliminate any deviation, reservation, and omission of any basic detail, in which:

a) Deviation refers to any deviation from requirements specified under bidding documents;

b) Reservation refers to the fact that investors lay out conditions that are restrictive or showing other than full compliance with requirements under bidding documents;

c) Omission of basic details refers to investors’ failure to provide any or all information and/or documents according to request under bidding documents.

4. As long as the bids qualify based on requirements under bidding documents, procuring entities can accept the errors that are other than deviations, reservations, or omission in bidding documents. In which, the deviations, reservations, and omission mean deviations, reservations, and omission whose acceptance or revision or replacement will lead to:

a) Significant impact on scope and technical, technological, quality requirements of works and infrastructures;

b) Significant limitation and inconsistency with bidding documents in powers of procuring entities, competent authorities, or obligations of investors under contracts;

c) Unfair impact on competitive position of other investors having bids qualifying based on requirements under the bidding documents;

5. Bids that do not qualify based on requirements under bidding documents will be eliminated; deviations, reservations, and omissions in bids are not allowed to be revised and rectified in order to make the bid qualify.

Best Regards!

Related Posts
LawNet
What is a digital signature certificate? What are regulations on classification of digital signature certificates in Vietnam?
LawNet
List of templates of documents related to special investment procedures in 2025 in Vietnam
LawNet
What is the template of the Report on the results of construction design appraisal in 2025 in Vietnam?
LawNet
What is PPP project contract in Vietnam? What are the types of PPP project contracts in Vietnam?
LawNet
What is a PPP project? Which PPP projects are classified according to the authority for investment policy decision in Vietnam?
LawNet
Which packages shall be applied for selection of contractors in special cases in Vietnam?
LawNet
What is bidding in advance according to the law in Vietnam? Which packages can be subjected to bidding in advance in Vietnam?
LawNet
What are forms and methods for selecting investors in Vietnam in 2025?
LawNet
List of business lines and business establishments encouraged to invest in or relocate to industrial clusters in Vietnam
LawNet
What is the template of the Appraisal Report of Construction Design Following Basic Design in Vietnam according to Decree 175?
Lượt xem: 0
Latest Post

Đơn vị chủ quản: Công ty THƯ VIỆN PHÁP LUẬT.
Chịu trách nhiệm chính: Ông Bùi Tường Vũ - Số điện thoại liên hệ: 028 3935 2079
P.702A , Centre Point, 106 Nguyễn Văn Trỗi, P.8, Q. Phú Nhuận, TP. HCM;