Appraisal Time for Pre-Feasibility Study Reports of Group A, B, C Public Investment Programs and Projects
Translation
How long is the period for appraising the pre-feasibility study report, the report proposing investment policy for programs, public investment projects in group A, B, C? Are there differences between the groups of projects?
According to the provisions in Clause 6, Article 9 of Decree 40/2020/ND-CP guiding the Law on Public Investment, this content is regulated as follows:
The time for appraising the pre-feasibility study report, the project proposal report for investment policy of programs, public investment projects in groups A, B, C from the date the Appraisal Council or the appraising authority receives a complete and valid dossier is as follows:
- National target program: Not more than 60 days;
- Public investment program (excluding national target program): Not more than 45 days;
- Group A project: Not more than 45 days;
- Group B, C projects: Not more than 30 days;
In case the dossier is not valid or the content in the pre-feasibility study report, the project proposal report for investment policy of the program, project does not comply with the provisions at Articles 29, 30, 31 of the Law on Public Investment, within no more than 10 days from the date of receiving the dossier, the Appraisal Council or the appraising authority shall provide written opinions to the submitting agency to supplement the dossier or complete the content of the pre-feasibility study report, project proposal report for investment policy of the program, project.
Regarding public investment projects in groups A, B, C: Please refer to Articles 8, 9, and 10 of the Law on Public Investment 2019.
Thus, the time for appraising the report varies between different programs and groups of investment projects.
The above is the supportive content regarding the appraisal content of investment policy for public investment projects in groups A, B, C.
Best regards!