What are basic activities involved in acceptance testing of investment projects for information technology application funded by state budget in Vietnam? What are regulations on testing or commissioning of investment projects for information technology application funded by state budget in Vietnam? What are regulations on acceptance testing and transfer of completed project items of investment projects for information technology application funded by state budget in Vietnam?

Best regards!

What are basic activities involved in acceptance testing of investment projects for information technology application funded by state budget in Vietnam?

Pursuant to Article 9 of the Circular 24/2020/TT-BTTTT stipulating basic activities involved in acceptance testing of investment projects for information technology application funded by state budget in Vietnam as follows:

1. Conducting the testing or commissioning before the acceptance testing and transfer of the project's products and items.

2. Performing steps in acceptance testing and transfer of project’s products and items as legally prescribed.

What are regulations on testing or commissioning of investment projects for information technology application funded by state budget in Vietnam?

Pursuant to Article 10 of the Circular 24/2020/TT-BTTTT stipulating testing or commissioning of investment projects for information technology application funded by state budget in Vietnam as follows:

1. Project’s products or items must be tested or commissioned at the minimum of one beneficiary unit before being accepted, transferred and put to use.

2. For technical infrastructure systems, equipment and commercial software, the contractor shall take charge of, and cooperate with the investor in, conducting the commissioning.

a) Contents and sequence of the commissioning activity shall follow the instructions given in Sub-Appendix 2a of Appendix II to this Circular;

b) Commissioning results shall be documented in a report by the implementing contractor.

3. For internal software, depending on the level of quality requirements and actual conditions, the investor shall consider issuing the decision to apply the testing or commissioning approach, and shall be responsible for their decision.

a) Contents and sequence of the commissioning activity shall follow the instructions given in Sub-Appendix 2b of Appendix II to this Circular. During the internal software commissioning process, the investor should take control of the quality of software to ensure their conformance to non-functional requirements on the basis of a report on results of the test conducted by the contractor as prescribed at point d Clause 5 Article 4 of this Circular. Results of commissioning of internal software shall be reported by the investor;

b) Contents and sequence of the commissioning steps shall follow the instructions given in Sub-Appendix 2c of Appendix II to this Circular. Test results shall be reported in writing by the investor (in case of conducting the test of their own accord), or by the independent testing unit (in case of hiring an independent testing unit to conduct the test).

What are regulations on acceptance testing and transfer of completed project items of investment projects for information technology application funded by state budget in Vietnam?

Pursuant to Article 11 of the Circular 24/2020/TT-BTTTT stipulating acceptance testing and transfer of completed project items of investment projects for information technology application funded by state budget in Vietnam as follows:

1. Project’s products or items shall be accepted and handed over for use in accordance with Article 35 of Decree No. 73/2019/ND-CP.

2. Conditions for the acceptance testing of project's products or items

a) These products or items must be fully complete in terms of the volume, quality, progress, contractual requirements and approved detailed designs;

b) In order to be eligible for testing or commissioning, products or items must meet the quality requirements specified in Article 34 of Decree No. 73/2019/ND-CP and Article 10 of this Circular.

3. Investors and related units shall agree on the contents of the acceptance testing, time and place of acceptance testing and transfer after all of the conditions specified in Clause 2 of this Article are satisfied. Acceptance testing and transfer results shall be recorded in writing by using the form provided in Appendix I to this Circular.

4. Products or items obtained from the projects may only be handed over to the investor after they are accepted to meet the quality requirements.

5. The implementing contractor shall be responsible for handing over products or items to the investor, and enclosing the following documents:

a) Documents on completion of project’s products or items provided in the list given in Appendix IV to this Circular;

b) Software installation program kits and source codes (if any);

c) User, administration and operation manuals; materials for user training, administration and operation; maintenance procedure documents (if any); guidance on techniques, standards and regulations (if any). Main contents of administration, operation and maintenance of project’s products or items shall follow guidelines given in Sub-Appendixes 3a and 3b to Appendix III to this Circular;

d) Technical documents used for connection purposes as legally prescribed (with respect to projects with data connection and sharing between ministries, central agencies and localities);

dd) Documents created in each stage in the process of building, development, upgradation and expansion of the software which are subject to contractual terms and conditions.

Transfer documents specified in this clause must be clearly defined in the contract and constitute a part of the product of the whole project.

Best regards!

Related Posts
LawNet
Vietnam: Use of digital signatures to conduct money transfer transactions in the Social Insurance Sector
LawNet
Vietnam: How many trained technicians are civil cryptographic service providers required to have at least?
LawNet
What are details of Form 02/DK-TDT - Application form for change or addition to the information registered for e-tax transactions in Vietnam?
LawNet
Procedures for issuance of license for operating two types of news media in Vietnam
LawNet
Résumé of the person proposed to be the Editor-in-Chief in Vietnam
LawNet
What are instructional viewpoints stated in Scheme 06 of the Government of Vietnam?
LawNet
Does the district-level police authority in Vietnam have the power to inspect the operations of gaming centers?
LawNet
Vietnam: What are the regulations on public utility telecommunications services according to regulations for postpaid terrestrial fixed broadband internet access?
LawNet
Procedures for online contractor selection under single-stage and two-envelope bidding procedure in Vietnam
LawNet
Is the permission required for to repost news or articles by news aggregator websites in Vietnam?
Lượt xem: 0
Latest Post

Đơn vị chủ quản: Công ty THƯ VIỆN PHÁP LUẬT.
Chịu trách nhiệm chính: Ông Bùi Tường Vũ - Số điện thoại liên hệ: 028 3935 2079
P.702A , Centre Point, 106 Nguyễn Văn Trỗi, P.8, Q. Phú Nhuận, TP. HCM;