Circular No. 15/2016/TT-BXD of the Ministry of Construction of Vietnam providing guidelines on the issuance of construction permits shall be applied for new construction works, phase-based construction works, projects and detached houses from August 15, 2016.

According to Circular No. 15/2016/TT-BXD of the Ministry of Construction of Vietnam, an applicant for construction permit shall have right to request the construction licensing authority to explain, instruct and comply with regulations on the issuance of construction permit to construct the work (according to Clause 4 Article 102 of the Law on Construction 2014 of Vietnam). An applicant shall also have the right to request construction licensing authorities to issue construction permits to the works which are exempted from construction permits. Moreover, the applicant shall have the right to complain or denounce for violations against regulations on the issuance of construction permit.

Application for construction permit for new construction works includes:

- The application form for construction permit using the prescribed form;

- The copy or the file containing the photograph of the original of one of the documents proving the land title as referred to in the law on land;

- The copies or files containing photographs of two sets of original technical design drawings or construction design drawings which have been approved as referred to in the law on construction, each set consists of:

Non-linear construction works

Linear construction works in urban area

- The site plan showing the location of the work on the land lot with scale of 1:100 - 1:500, enclosed with the work location diagram;

- Principal plans, elevations and sections of the work with scale of 1:50 - 1:200;

- Foundation plans with scale 1:100 - 1:200 and footing sections with scale of 1:50, enclosed with diagrams for connecting the work with other technical structures such as traffic system, water supply and drainage, sewage treatment system, power supply, communications system and other infrastructures related to the work with scale of 1:50 - 1:200.

- The diagram of the linear work with scale 1:100 - 1:500;

- Master plans or contour drawing of the work with scale of 1:500 - 1:5000;

- Principal cross sections of the linear work with scale of 1:50 - 1:200;

With regard to underground works, the following documents must be supplemented:

- Cross sections and longitudinal sections which show the depth of the work with scale of 1:50 - 1:200;

- Diagram of connection to the infrastructure outside the work with scale 1:100 - 1:500. 

Religious construction works: The application for construction work includes the documents prescribed above and the copy or the file containing the photograph of the original written approval by the competent authority for the necessity and the scale of the religious construction work.

View details at Circular No. 15/2016/TT-BXD of the Ministry of Construction of Vietnam, effective from August 15, 2016.

>> CLICK HERE TO READ THIS ARTICLE IN VIETNAMESE

33 lượt xem



  • Address: 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City
    Phone: (028) 7302 2286
    E-mail: info@lawnet.vn
Parent company: THU VIEN PHAP LUAT Ltd.
Editorial Director: Mr. Bui Tuong Vu - Tel. 028 3935 2079
P.702A , Centre Point, 106 Nguyen Van Troi, Ward 8, Phu Nhuan District, HCM City;