What are the preparation steps in the process of implementing the latest Vietnamese Communist Party financial inspection in 2022?

According to Section I, the process promulgated together with Decision 354-QD/UBKTTW in 2021 of Vietnam on the process of performing the Party financial inspection:

- Based on the annual work program of the Committee or the tasks assigned by the Vietnamese Communist Party Committee or Committee, the area monitoring officer proposes and reports to the Standing Committee of the Committee: Contents; party organization is examined; inspection plan (timeline of inspection, working time of the delegation...) and expected members of the inspection team (team) (referred to as inspection team).

- Standing committee considers and issues a decision and inspection plan (form as prescribed).

- The inspection team develops an outline to suggest the self-inspection report (the prescribed form) so that the inspected party can prepare the report; the working schedule of the delegation; meet the delegation to announce the plan, assign tasks to each member of the delegation; Prepare documents and related documents for inspection.

What is the process of the financial inspection of the Vietnamese Communist Party in 2022? When will be tested by online meeting?

What is the process of the financial inspection of the Vietnamese Communist Party in 2022? When will be tested by online meeting?

What are the steps in the process of implementing the latest Vietnamese Communist Party financial inspection in 2022?

According to Section II, the process promulgated together with Decision 354-QD/UBKTTW in 2021 of Vietnam on the process of performing the Party financial inspection:

Step 1: Committee members are assigned to direct and represent the inspection team to work with representatives of the inspected party organization to implement decisions and plans; agree on a working schedule; request the inspected party organization to prepare a written self-inspection report, to provide relevant records and documents; propose to direct relevant units, organizations and individuals to coordinate in implementation.

+ In case of necessity, it will be conducted in the form of an online meeting or by sending documents by official mail.

Step 2: The inspected party organization prepares a self-inspection report (in writing) according to the proposed outline and documents and records; sent to the Inspection Committee (via the inspection team).

Step 3: The inspection team conducts verification and verification:

+ Reviewing self-inspection reports, accounting records, documents, books, and vouchers related to inspection contents and financial statements of the inspected party organization; working with relevant organizations and individuals.

+ If it is necessary to adjust or supplement contents, time, objects of inspection, members of the inspection team, or have professional or technical problems that need expertise, the head of the inspection team shall report to the members of the Steering Committee for consideration of the decision.

+ The inspection team works with the inspected party organization on the contents that need to be explained, supplemented, and clarified. Prepare a draft test report (form as prescribed).

+ (If it is found that the violation is clear enough to require disciplinary action and the inspected party organization voluntarily acknowledges the violation and self-reviews the disciplinary form, the head of the inspection team or a member of the Committee shall only The inspection team reports to the Committee or the Standing Committee to consider and decide to combine the implementation of the process of reviewing and enforcing party discipline with the process of checking party finances.

+ Before deciding to discipline, comrades of the Inspection Committee direct the delegation to meet with representatives of the violating party organizations to listen to their opinions and report (enclosed with the self-criticism of the violators) at the meeting. meeting of the Inspection Committee. Or representatives of the violating party organizations have the right to directly present their opinions or report in writing to the Inspection Committee at the conference for consideration and disciplinary action and must strictly comply with the decision after the decision is made).

Step 4: Organize a conference (the party organization is inspected to organize and preside over, record the minutes of the conference) for the inspection team to approve the draft report on inspection results; inspected party organizations present their explanations and self-recognition forms of discipline (if any); conference to discuss and give opinions on the draft report on inspection, verification and verification results on inspection contents and make written proposals (if any).

+ In case of necessity, it will be conducted in the form of an online meeting or by sending documents by official mail.

Step 5: The inspection team continues to verify and verify the unclear contents (if any); complete the draft test report; exchange ideas with the head (site monitoring unit; not the team leader or inspection team member) on the inspection results; report to consult with members of the Steering Committee of the delegation before submitting to the inspection committee.

What are the final steps in the process of implementing the latest Vietnamese Communist Party financial inspection 2022?

According to Section III of the process promulgated together with Decision 354-QD/UBKTTW in 2021 of Vietnam on the process of performing the Vietnamese Communist Party financial inspection:

- The examination committee considers and concludes:

+ The inspection team reports the test results; fully presents opinions of the inspected party organization, related organizations, and individuals.

+ The Committee concludes and votes on the decision on disciplinary enforcement or proposes the competent authority to decide on disciplinary enforcement (if any).

- The unit monitoring the area shall report in writing to the Committee on the results and activities of the inspection team.

- The inspection team completes the inspection result report; coordinates with (the unit or general officer) to complete the notification of inspection conclusions, and disciplinary decisions, or report to the competent authorities to enforce the discipline of the violating party organization or member (if any), report to members of the steering committee of the delegation before submitting to the standing committee for signature and promulgation.

- Members of the steering committee and representatives of the inspection team shall notify the inspection conclusions and announce the disciplinary decisions (if any) to the inspected party organization and the relevant party organization and party members.

+ In case of necessity, it will be conducted in the form of an online meeting or by sending documents by official mail.

- The inspection team meets to draw experience; The team leader shall make a written comment and assessment of each member of the inspection team and send it to the heads of the units with officials participating in the delegation; prepare and file records according to regulations.

- The Department of Localities, units, and officials monitoring the area shall supervise the observance of conclusions and decisions of the Committee.

Above is the process of implementing the latest Vietnamese Communist Party financial inspection in 2022.