What is the latest application form for appraisal of construction design following basic design in Vietnam?
- What is the latest application form for appraisal of construction design following basic design in Vietnam?
- What is included in the application for appraisal of construction design following basic design in Vietnam?
- What is the time limit for appraisal of construction design following basic design of construction authorities in Vietnam?
What is the latest application form for appraisal of construction design following basic design in Vietnam?
The application form for appraisal of construction design following basic design is Form No. 04 specified in Appendix I issued together with Decree No. 15/2021/ND-CP. Below is an image of the application form for appraisal of construction design following basic design:
Download the application form for appraisal of construction design following basic design: Click here.
What is the latest application form for appraisal of construction design following basic design in Vietnam? (Image from the Internet)
What is included in the application for appraisal of construction design following basic design in Vietnam?
Pursuant to Clause 3, Article 37 of Decree No. 15/2021/ND-CP stipulating as follows:
Application for appraisal of design following basic design to construction authorities
1. The applicant shall submit 1 set of application for appraisal to the construction authority. The application for appraisal shall be submitted in person or by post.
2. The application for appraisal shall ensure the legality and conformity with the matters seeking appraisal. The application for appraisal shall be considered valid when it has full contents specified in clause 3 hereof, is made in proper format, primarily written in Vietnamese and certificated by the applicant. The part of the architectural design documents in the construction design documents (if any) should comply with the provisions of the law on architecture.
3. An application for appraisal of construction design following basic design includes:
a) Application form for appraisal using the form No. 04 of Appendix I hereto;
b) The enclosed legal documents, including: a decision on approval for the construction project together with an approved feasibility study report; a notice of appraisal result of the construction authority and the basic design drawings enclosed with a certification stamp (if any); a report on the construction design assessment result of the assessment consulting contractor certified by the investor (if required); a document on evaluation and approval of fire safety design, result of environmental impact assessment in accordance with the law on environmental protection (if required) and other relevant documents;
Procedures for fire safety shall be completed in parallel, no fire safety document is required at the time of submission of the appraisal application, but the completion of fire safety procedures must be sent to the construction authority before the deadline for notification of appraisal result;
c) Construction survey documents approved by the investor; construction design documents of the construction design step seeking appraisal;
d) Construction eligibility certificate codes of the survey contractor, construction design contractor, assessment contractor; construction practice certificate codes of the titles of construction survey president, design president, chairperson; assessment president, chairperson; construction operating license of foreign contractor (if any);
dd) For a work funded by public investment capital, state capital other than public investment capital that requires appraisal of construction estimate, in addition to the requirements specified in point a, point b, point c and point d of this clause, the dossier must also have construction cost estimates; relevant information and data on relevant prices and norms to determine construction cost estimates; quotations, valuation results (if any).
Thus, according to the above regulations, an application for appraisal of construction design following basic design includes:
- Application form for appraisal using the form No. 04 of Appendix I enclosed with Decree No. 15/2021/ND-CP;
- The enclosed legal documents, including:
+ A decision on approval for the construction project together with an approved feasibility study report;
+ A notice of appraisal result of the construction authority and the basic design drawings enclosed with a certification stamp (if any);
+ A report on the construction design assessment result of the assessment consulting contractor certified by the investor (if required);
+ A document on evaluation and approval of fire safety design, result of environmental impact assessment in accordance with the law on environmental protection (if required) and other relevant documents;
+ Construction survey documents approved by the investor; construction design documents of the construction design step seeking appraisal;
+ Construction eligibility certificate codes of the survey contractor, construction design contractor, assessment contractor; construction practice certificate codes of the titles of construction survey president, design president, chairperson; assessment president, chairperson; construction operating license of foreign contractor (if any);
+ For a work funded by public investment capital, state capital other than public investment capital that requires appraisal of construction estimate, in addition to the requirements, the dossier must also have construction cost estimates; relevant information and data on relevant prices and norms to determine construction cost estimates; quotations, valuation results (if any).
What is the time limit for appraisal of construction design following basic design of construction authorities in Vietnam?
Pursuant to Clause 7 Article 38 of Decree No. 15/2021/ND-CP, the time limits for appraisal of construction design following basic design of construction authorities in Vietnam from the date on which the satisfactory dossier is received:
- Within 40 days regarding class I and special class construction works;
- Within 30 days regarding class II and class III construction works;
- Within 20 days regarding remaining construction works.