What is the form of Certificate of inspection of machinery, equipment, and technological lines used in the project in Vietnam?
- Which entity shall issue inspection certificate to inspect machinery, equipment, and technological lines in projects in Vietnam?
- What is the form of Certificate of inspection of machinery, equipment, and technological lines used in the project in Vietnam?
- What are the procedures for project technology determination in Vietnam?
Which entity shall issue inspection certificate to inspect machinery, equipment, and technological lines in projects in Vietnam?
Pursuant to Article 5 of Decision 29/2023/QD-TTg 2023 on inspection certificates, designated inspection bodies:
Inspection certificates, designated inspection bodies
1. Inspection certificate is issued by a designated inspection body to inspect machinery, equipment, and technological lines in projects as per the law.
The validity of the inspection certificate is 12 months from the date of issuance of the certificate.
2. The inspection body has been granted a certificate of registration for inspection as specified in Decree No. 107/2016/ND-CP dated July 1, 2016 of the Government regulating eligibility requirements for conformity assessment, including the field of inspection of machinery, equipment, and technological lines, which is registered with a competent authority that is designated to inspect machinery, equipment, and technological lines in projects.
3. Designated inspection bodies of used machinery, equipment, and technological lines that are imported under Decision No. 18/2019/QD-TTg dated April 19, 2019 of the Prime Minister may register with competent authorities for supplementing inspection fields/scope of machinery, equipment, and technological lines.
Inspection certificate is issued by a designated inspection body to inspect machinery, equipment, and technological lines in projects as per the law.
Note: The validity of the inspection certificate is 12 months from the date of issuance of the certificate.
Which entity shall issue inspection certificate to inspect machinery, equipment, and technological lines in projects in Vietnam? (Image from the Internet)
What is the form of Certificate of inspection of machinery, equipment, and technological lines used in the project in Vietnam?
Certificate of inspection of machinery, equipment, and technological lines used in the project is made using Form No. 03 is specified in the Appendix to Decision 29/2023/QD-TTg 2023.
Download the form of Certificate of inspection of machinery, equipment, and technological lines used in the project
What are the procedures for project technology determination in Vietnam?
Pursuant to Clause 2, Article 4 of Decision 29/2023/QD-TTg 2023, the procedures for project technology determination are prescribed as follows:
Step 1: The investor sends one set of application for project technology determination, in person, by post, or via the online public service portal to the agency that leads the technology determination according to their authority as prescribed in Points a and b, Clause 11, Article 27 of Decree No. 31/2021/ND-CP (hereinafter referred to as the lead agency).
Step 2: If the application is incomplete or invalid and the investor submitted it in person at the single-window division of the lead agency, the lead agency shall immediately return it to the investor with clear instructions on necessary amendments or additions.
If the application is incomplete or invalid and the investor submitted it via the online public service portal or by post, after 2 working days of receiving the application, the lead agency shall request the investor for necessary amendments or additions.
Step 3: After 3 working days of receiving a complete and valid application, the lead agency shall request the environmental authority and a specialized authority at the same level with the lead agency in writing for their consultation. Where necessary, the lead agency may also seek expert opinions from independent organizations or individuals to assist in the technology determination process.
Step 4: Within 15 working days, the agencies that are consulted, independent organizations and experts shall have their written opinions sent to the lead agency
Step 5: For large-scale projects with complex technology, where necessary, the lead agency may, within 20 working days of receiving a complete application, establish a Science and Technology Advisory Council (as outlined in Clause 3) and undertake an on-site visit to further assess the project technology.
Step 6: Within 5 working days of receiving all required feedback (agencies, Council, independent organizations, and experts), the lead agency shall issue a written determination on the project's technology, using Form No. 04 (Appendix)