Vietnam: What does the application for approval of the inland waterway traffic safety plan include? - T. T (Ha Nam)

Vietnam: What does the application for approval of the inland waterway traffic safety plan include?

Based on the provisions of Clause 4, Article 6 of Decree 159/2018/ND-CP on the plan for ensuring traffic safety for dredging activities in maritime waters and inland waterway areas as follows:

Plans for assurance of traffic safety for dredging operations occurring within seaport water and inland water areas

...

4. The application requesting approval for the plan for assurance of traffic safety includes:

a) A document requesting approval of the plan for assurance of traffic safety;

b) A copy of the investment decision for the construction project;

c) A copy of the decision approving the construction project design;

d) A copy of the general layout plan of the project;

dd) The original plan for assurance of traffic safety.

5. Procedure for receiving and processing the application:

The competent authority specified in Clause 3 of this Article receives the application. If the application is not valid, within 03 working days from the date of receipt, the competent authority must guide the completion of the application as prescribed in this Decree; if the application is valid, within 03 working days from the date of receipt, the competent authority must seek the opinions of relevant agencies and units; within 05 working days from the date of receiving all opinions, it must issue a document approving the plan for assurance of traffic safety and send it directly or via postal system to the investor; if disapproved, it must have a written response stating the reasons.

...

Thus, the application requesting the approval of the inland waterway traffic safety plan includes:

- A document requesting approval of the plan for assurance of traffic safety;

- A copy of the investment decision for the construction project;

- A copy of the decision approving the construction project design;

- A copy of the general layout plan of the project;

- The original plan for assurance of traffic safety.

Hồ sơ đề nghị phê duyệt phương án bảo đảm an toàn giao thông đường thủy nội địa gồm có những gì?

Vietnam: What does the application for approval of the inland waterway traffic safety plan include? (Image from the Internet)

Vietnam What does the inland waterway signaling system include?

Based on the provisions of Article 12 of the Law on Inland Waterway Traffic 2004 on inland waterway signaling as follows:

Inland waterway signaling

...

2. The inland waterway signaling system includes:

a) Channel marking signals to indicate channel boundaries or vessel directions;

b) Hazard marking signals to indicate where there are obstacles or other dangers on the channel;

c) Informative guide signals to provide prohibitions, restrictions, or guidance on situations related to the channel.

3. Inland waterway routes that have been announced and managed must be equipped and maintained with an inland waterway signaling system.

...

Thus, the inland waterway signaling system includes:

- Channel marking signals to indicate channel boundaries or vessel directions;

- Hazard marking signals to indicate where there are obstacles or other dangers on the channel;

- Informative guide signals to provide prohibitions, restrictions, or guidance on situations related to the channel.

What are the policies for the development of inland waterway traffic in Vietnam?

Based on the provisions of Article 5 of the Law on Inland Waterway Traffic 2004 with phrases replaced by Clause 7, Article 4 of the Law amending and supplementing a number of Articles of 37 Laws related to planning 2018 on policies for developing inland waterway traffic as follows:

Policies for the development of inland waterway traffic

1. The State prioritizes investment in the development of inland waterway infrastructure on key inland waterway traffic routes, key economic areas, remote areas with advantages in inland waterway traffic compared to other types of traffic.

2. The State encourages and facilitates Vietnamese organizations and individuals, as well as foreign organizations and individuals, to invest in developing inland waterway infrastructure, applying advanced science and technology, training specialized human resources, and investing in the business and exploitation of inland waterway transport to sustainably develop inland waterway traffic.

Thus, the policies for the development of inland waterway traffic are specified as follows:

- The State prioritizes investment in the development of inland waterway infrastructure on key inland waterway traffic routes, key economic areas, remote areas with advantages in inland waterway traffic compared to other types of traffic.

- The State encourages and facilitates Vietnamese organizations and individuals, as well as foreign organizations and individuals, to invest in developing inland waterway infrastructure, applying advanced science and technology, training specialized human resources, and investing in the business and exploitation of inland waterway transport to sustainably develop inland waterway traffic.