According to Clause 1, Article 37 of Circular 08/2022/TT-BKHDT stipulating the roadmap for applying online contractor selection in Vietnam in 2022 as follows:

"Article 37. Roadmap for online selection of contractors
1. In 2022
a) Organize the online selection of contractors for all (100%) bidding packages applying the form of open bidding and competitive offers in the field of goods, non-consulting services, and consulting services that are available for sale. the bidding package price is not more than 10 billion VND and in the field of construction and installation, the package price is not more than 20 billion VND, except for mixed bidding packages, the bidding package applies the method of two stages, one dossier bag, two stages, two dossier bags. profile:
b) The organization of online selection of contractors during the year must ensure that the total number of bidding packages reaches at least 80% of the number of bidding packages and at least 70% of the total value of the bidding packages, applying the form of open bidding, offering public tenders. competitive goods, except for mixed bidding packages, bidding packages applying the method of two stages, one dossier bag, two stages, two dossier bags;
c) Organize online selection of contractors for all (100%) bidding packages applying the form of open bidding or competitive offers using state capital for procurement in order to maintain the regular operation of the agency. state agencies, political organizations, socio-political organizations, socio-political-professional organizations, socio-professional organizations, social organizations, units of the people's armed forces, public non-business units, except for mixed bidding packages, bidding packages apply the method of two stages, one dossier bag, two stages, two dossier bags."

Thus, from August 1, 2022, the roadmap for applying online contractor selection in 2022 for bidding packages applying the open bidding form is 100% according to the above regulations

New: What is the roadmap for applying online contractor selection in Vietnam from 2022 according to Circular 08/2022/TT-BKHĐT?

New: What is the roadmap for applying online contractor selection in Vietnam from 2022 according to Circular 08/2022/TT-BKHĐT?

What is the roadmap for applying online contractor selection in Vietnam in 2023?

According to Clause 2, Article 37 of Circular 08/2022/TT-BKHDT stipulating the roadmap for applying online contractor selection in Vietnam in 2023 as follows:

"Article 37. Roadmap for online selection of contractors
..
2. In 2023
a) Organize online selection of contractors for all (100%) bidding packages applying the form of open bidding, limited bidding, competitive offers in the field of goods (including drugs), construction Installation, non-consulting services, and private services still have a package price of not more than VND 200 billion, except for mixed bidding packages, bidding packages applying the method of two stages, one dossier bag, two stages, two dossier bags:
b) The organization of online selection of contractors during the year must ensure that the total number of bidding packages reaches at least 90% of the number of bidding packages and at least 80% of the total value of bidding packages applying the form of open bidding or public bidding. limited bidding, competitive offers, except for mixed bidding packages, bidding packages applying the method of two stages, one dossier bag, two stages, two dossier bags,
c) Organize online selection of contractors for all (100%) bidding packages applying the form of open bidding or competitive offers using state capital for procurement in order to maintain the regular operation of the agency. state agencies, political organizations, socio-political organizations, socio-political-professional organizations, socio-professional organizations, social organizations, units of the people's armed forces, public non-business units, except for mixed bidding packages, bidding packages applying the method of two stages, one dossier bag, two stages, two dossier bags..."

Thus, from August 1, 2022, the roadmap for applying online contractor selection in 2023 for all bidding packages applying the open bidding form according to the above regulations.

What is the roadmap for applying online contractor selection in Vietnam from 2024 onwards?

According to Clause 3, Article 37 of Circular 08/2022/TT-BKHDT stipulating the roadmap for applying online contractor selection in Vietnam from 2024 onwards as follows:

"Article 37. Roadmap for online selection of contractors
..
3. Year 2024 onwards
a) Organize online selection of contractors for all (100%) bidding packages applying the form of open bidding, limited bidding, competitive offers in the field of goods (including drugs), construction installation, non-consulting services, and consulting services with a bidding package price not exceeding VND 500 billion, except for mixed bidding packages, bidding packages applying the method of two stages, one dossier bag, two stages, two dossier bags,
b) The organization of online selection of contractors during the year must ensure that the total number of bidding packages reaches at least 95% of the number of bidding packages and at least 90% of the total value of bidding packages using open bidding, public bidding. limited bidding, competitive offers, except for mixed bidding packages, bidding packages applying the method of two stages, one dossier bag, two stages, two dossier bags,
c) Organize online selection of contractors for all (100%) bidding packages applying the form of open bidding or competitive offers using state capital for procurement in order to maintain the regular operation of the agency. state agencies, political organizations, socio-political organizations, socio-political-professional organizations, socio-professional organizations, social organizations, units of the people's armed forces, public non-business units, except for mixed bidding packages, bidding packages apply the method of two stages, one dossier bag, two stages, two dossier bags.

Thus, from August 1, 2022, the roadmap for applying online contractor selection from 2024 onwards for all bidding packages applying the open bidding form according to the above regulations.

Circular 08/2022/TT-BKHDT takes effect from August 1, 2022.