How will projects with out-of-budget capital that have been allocated, leased, or changed land use purposes by the State but have been delayed in implementation in Hanoi?
- Classification and handling of non-budget capital projects that have had a policy decision but have not been allocated or leased land by the State in Hanoi?
- How will non-budget capital projects that have been allocated, leased, or changed land use purposes by the State but have been delayed in implementation in Hanoi?
- How should information about slow-moving and slow-deploying projects in Hanoi be handled?
Classification and handling of non-budget capital projects that have had a policy decision but have not been allocated or leased land by the State in Hanoi?
Pursuant to Section II, Part B of the Plan 160/KH-UBND in 2022, promulgated by the Hanoi People's Committee on June 8, 2022 as follows:
- For projects that have had a policy decision (approval of investment policy, approval of investment, written assignment of the Investor to study) which is past the project implementation progress but has not yet been assigned by the State. land, land lease: Assign the Department of Planning and Investment to assume the prime responsibility for, and coordinate with the city's Departments, branches and People's Committees of districts, towns in implementation. To be responsible for the adjustment of investment projects in accordance with the law, for the lengthy implementation of adjustment procedures, which affects the project implementation schedule, leading to delay in construction investment and land acquisition. to use in accordance with regulations.
Thus, the classification and handling of non-budget capital projects that have had a policy decision but have not yet been allocated or leased land by the State in Hanoi is carried out according to the above guidance.
How will projects with out-of-budget capital that have been allocated, leased, or changed land use purposes by the State but have been delayed in implementation in Hanoi?
How will non-budget capital projects that have been allocated, leased, or changed land use purposes by the State but have been delayed in implementation in Hanoi?
Pursuant to Section II, Part B of the Plan 160/KH-UBND in 2022, promulgated by the Hanoi People's Committee on June 8, 2022 as follows:
- Project team that has not cleared the ground (To last for many years or the investor does not contact or coordinate with local authorities to carry out site clearance work): Assign People's Committees of districts, towns and cities The commune shall assume the prime responsibility for, and coordinate with the city's departments and agencies in, implementation. Responsible for the completion of site clearance for local projects.
Strictly implement and completely complete the work of land acquisition in the field for the violating projects for which the decision on land recovery has been issued, the decision on land allocation and land lease has been annulled (for the decide to assign the district-level People's Committee or the district-level land fund development center to implement) to manage and propose a land use plan in accordance with the planning or organize an auction of land use rights, bid for projects using prescribed land.
- The project team has completed site clearance, but has not yet invested in construction: Assign the Department of Natural Resources and Environment to assume the prime responsibility for, and coordinate with the City Departments and the People's Committee of the district in the implementation. To take responsibility for the results of settlement of dossiers related to decisions on change of land use purpose; adjust the decision on land allocation, land lease, change of land use purpose for non-budget capital investment projects using land.
Continue to inspect projects that have not been put into use, and compile a dossier of land use extension for 24 months as prescribed in Point i, Clause 1, Article 64 of the 2013 Land Law. The City branch shall organize a post-inspection and must give clarifications, be responsible for determining the reason why the land-using organization is slow to put the land into use due to the impact of the epidemic; due to the implementation of procedures for planning adjustment; due to the implementation of procedures on project adjustment; related to the fulfillment of financial obligations of the land user; related to the settlement of petitions, complaints and denunciations of citizens; and other contents related to the project's delay in progress, delay in putting the land into use due to objective and force majeure reasons.
- The project team has completed site clearance, is under construction (or has built a part of the project but so far the investor is stopping the project implementation not according to the provisions of law): Assign the Department of Planning and Investment and Investment shall assume the prime responsibility for, and coordinate with the City's Departments of Industry and Trade and the People's Committee of the district, to immediately implement investment supervision measures, send written urging and request the Investor to accelerate the progress, commit to the roadmap, implementation time to soon put the project into use according to the schedule and regulations of law. Responsible for monitoring the project implementation progress of the investors to ensure the completion of the project according to the approved schedule.
- The project team is carrying out site clearance work (or has completed site clearance for part of the project but is now stopping the implementation: Assign People's Committees of districts, towns to assume the prime responsibility for, and coordinate with other relevant Departments of Planning and Investment). Responsible for the progress of site clearance to ensure the handover of land in the field to the investor for project implementation.
- Project group of debt financial obligations: Assign the City Tax Department to assume the prime responsibility for, and coordinate with the Department of Finance, city departments and district-level People's Committees to implement (especially projects with long-term financial obligations). , projects that owe large amounts of financial obligations). To be responsible for the progress of collecting tax arrears of projects that are late in paying financial obligations to ensure collection management in accordance with tax laws.
- The group of projects that are delayed due to objective reasons must adjust the planning in accordance with the general planning and zoning planning: Assign the Department of Architecture and Planning to assume the prime responsibility for, and coordinate with the Department of Planning and Investment, City Departments and District People's Committees implement. Be responsible for the planning adjustment related to the Projects, for the prolonged planning adjustment time leading to the slow progress of the Project and slow implementation. When the Investor proposes to adjust the master plan, he must consider and answer clearly whether the adjustment can be adjusted or not), as a basis for the City Departments to urge and request the Investor to continue implementing the project. judgment according to regulations.
Expeditiously complete zoning plans, serving as a basis for investors to study and adjust the Project according to regulations; Cases of delay in adjustment, failure to adjust, failure to implement the project according to the planning, failure to implement the project according to the planning should be considered as a condition for planning to withdraw the project, not continue to assign the project. for other projects.
Concentrating resources to solve and completely handle the existence of slow-moving projects due to objective reasons that have to adjust the planning, adjust investment projects to suit the general planning, the planning of administrative subdivisions. correction. Avoid the situation that the Investor takes advantage of the proposal to adjust the planning to prolong the implementation time of the project.
- Group of projects that are built against the planning, with the wrong construction permit, without a construction permit (for works requiring a construction permit), violating the construction order: Assign the People's Committees of districts, districts, the township shall assume the prime responsibility for, and coordinate with the Department of Construction, the Department of Planning and Architecture with, and relevant city departments in the implementation. Responsible for the management of construction order in the area.
Organize and supervise the implementation and construction of works for off-budget projects using land in order to promptly detect, prevent effectively and strictly handle cases of violations of law. self-construction according to the provisions of current law.
The Department of Construction has the responsibility to guide, urge and inspect the People's Committees of districts, towns in handling projects that violate the construction order; summarize results of violation handling of district-level People's Committees, report to City People's Committees (through the Department of Natural Resources and Environment for general synthesis.
- Other project groups (such as: Using land for improper purposes for leasing or lending land; delay in completing land procedures; improperly transferring or contributing capital with land use rights; illegally mobilizing capital; ;...): Assign City Departments and People's Committees of districts according to their functions and tasks to organize inspection and inspection, clarify objective causes, subjective causes, and clear solutions. to handle and propose measures to handle the test according to its competence and according to the provisions of law.
Accordingly, the handling of projects with out-of-budget capital that have been allocated, leased, or changed land use purposes by the State but have been delayed in implementation in Hanoi shall comply with the above regulations.
How should information about slow-moving and slow-deploying projects in Hanoi be handled?
Pursuant to Section II, Part B of the Plan 160/KH-UBND in 2022 promulgated by the Hanoi People's Committee on June 8, 2022 as follows:
- Implement publicity and transparency of information for projects that are behind schedule, slow to deploy, or violate the law on investment, planning, land, tax, and construction; Infringing projects shall be coerced, withdrawn or terminated in accordance with the provisions of law in order to create consensus and supervise the people and enterprises in the implementation.
- Assign City Departments: Planning and Investment, Natural Resources and Environment, Architectural Planning, Construction, Finance, City Tax Department, City electronic communication portal to be responsible for publicly implementing according to comply with the provisions of the law on land, investment, planning, tax and construction.
- Assign the district-level People's Committees to regularly direct the People's Committees of communes, wards and townships to organize publicity on local media such as loudspeakers, radio stations,...
- Request Hanoi Radio and Television Station, New Hanoi Newspaper, Economic and Urban Newspaper to have the responsibility to inform and publish free of charge about projects that are behind schedule, slow to implement, or violate the law on projects. investment, planning, land, tax, construction... for management agencies and people to participate in supervision.
Thus, information about slow-moving and slow-moving projects in Hanoi must be made public and transparent.