Guidelines for determining estimates and managing costs of demining mines and explosives in Vietnam

Guidelines for determining estimates and managing costs of demining mines and explosives in Vietnam
Đức Dũng

The Ministry of National Defense of Vietnam has promulgated Circular 123/2021/TT-BQP on guidance on identification cost estimates and cost management in mine clearance estimates.

According to this Circular, the estimated norm of mine clearance is based on 03 factors: (Appendix I)

(1) Necessary waste of materials;

(2) The amount of labor cost;

(3) Consumption of construction machinery.

The norm is built based on the completion of 1 unit of construction volume, in accordance with the work content and technical requirements.

In there:

- Material waste level is the required quantity of main and auxiliary materials;

- The level of labor waste is the number of direct working days of technicians and working days for checking mines and explosives;

- Construction machine wastage is the number of machine shifts and equipment directly working.

In addition, determining cost management as a basis for making estimates of demining, mines and explosives clearance specified in Appendix II includes: direct costs (T), general costs (C), taxes and other costs (K).

Circular 123/2021/TT-BQP  of Vietnam takes effect on November 5, 2021 and abolishes Circular 155/2013/TT-BQP and Decision 117/2007/QD-BQP .

 
 

>> CLICK HERE TO READ THIS ARTICLE IN VIETNAMESE

91 lượt xem



  • Address: 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City
    Phone: (028) 7302 2286
    E-mail: info@lawnet.vn
Parent company: THU VIEN PHAP LUAT Ltd.
Editorial Director: Mr. Bui Tuong Vu - Tel. 028 3935 2079
P.702A , Centre Point, 106 Nguyen Van Troi, Ward 8, Phu Nhuan District, HCM City;