What is road safety corridor? Determination of road safety corridor limits in Vietnam

What is road safety corridor? Determination of road safety corridor limits in Vietnam
Lê Trương Quốc Đạt

What is road safety corridor? What are the regulations on the determination of road safety corridor limits in Vietnam? - Thuy Linh (Binh Thuan)

What is road safety corridor? Determination of road safety corridor limits in Vietnam
What is road safety corridor? Determination of road safety corridor limits in Vietnam (Internet image) 

Regarding this issue, LawNet would like to answer as follows:

1. What is road safety corridor?

According to Article 15 of Decree 11/2010/ND-CP (amended in Decree 100/2013/ND-CP), the road safety corridor means land strips along both sides of road land used for assuring traffic safety and protecting road works. 

2. Determination of road safety corridor limits in Vietnam

According to Article 15 of Decree 11/2010/ND-CP (amended in Decree 100/2013/ND-CP), the road safety corridor limits in Vietnam are prescribed according to the road planning approved by the competent authority as follows:

- For roads outside urban centers: Depending on their planned technical grades, the width of a road safety corridor measuring from the road land to both sides is:

+ 17 meters for grade-I and grade-II roads;

+ 13meters for grade-III roads;

+ 09 meters for grade-IV and grade-V roads;

+ 04 meters for under grade-V roads;

- For urban roads, limitation of road safety corridor shall be the red boundaries under the planning approved by competent authorities.

- For expressways outside urban areas:

+ 17 meters, measured from land area of road to both sides;

+ 20 meters, measured from the outer edge of outermost structure to each side for dry bridges and trenches;

+ In case expressway with road at its side, based on technical level of road at its side to determine the safety corridor according to Clause 1 of Article 15 of Decree 11/2010/ND-CP (amended in Decree 100/2013/ND-CP) but not less than the limitation of safety corridors defined in point a, point b Clause 1 of Article 15 of Decree 11/2010/ND-CP (amended in Decree 100/2013/ND-CP). 

- For expressways inside urban areas:

+ Not less than 10 meters, measured from the outer edge of outermost structure to each side for trenches and dry bridges;

+ Being the red boundaries under the planning approved by competent authorities for trenches and dry bridges with road at sides and expressways with roads at sides.

+ From the outer edge of road to the red boundaries, but not less than 10 meters for expressways without roads at sides.

- For roads with safety corridors overlapping those of railways, the safety corridors of such roads and railways shall be demarcated on the principle that railway safety corridors will be prioritized, provided that they must not overlap road works.

In case a road and a railway are adjacent and share a longitudinal trench, the boundary between their safety corridors is the bottom edge of the trench on the higher roadside. If the heights of the two corridors are equal, the boundary between the safety corridors is the bottom edge of the trench on the railway side.

- For roads with safety corridors overlapping protection corridors of inland waterways, the boundary of these corridors is the edge of the natural bank.

- The handling of expressway safety corridors which have been determined before the effective day of Decree 11/2010/ND-CP (amended in Decree 100/2013/ND-CP):

+ In case where a project has been approved by competent authorities, and finished or in stage of compensation, support for ground clearance, the scope of  safety corridor will be keep intact according to the approved scope.

+ In case where a project has been approved by competent authorities, but has not yet performed compensation, support for ground clearance, the investor of project must re-approve or submit to competent authorities for re-approval of the scope of safety corridor in accordance with Decree 11/2010/ND-CP (amended in Decree 100/2013/ND-CP).

>> CLICK HERE TO READ THIS ARTICLE IN VIETNAMESE

281 lượt xem



  • Address: 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City
    Phone: (028) 7302 2286
    E-mail: info@lawnet.vn
Parent company: THU VIEN PHAP LUAT Ltd.
Editorial Director: Mr. Bui Tuong Vu - Tel. 028 3935 2079
P.702A , Centre Point, 106 Nguyen Van Troi, Ward 8, Phu Nhuan District, HCM City;