Types of construction permits in Vietnam under Law on Construction

What are the types of construction permits in Vietnam under Law on Construction? - Ngoc Linh (Tay Ninh)

Types of construction permits in Vietnam under Law on Construction
Types of construction permits in Vietnam under Law on Construction (Internet image)

Regarding this issue, LawNet would like to answer as follows:

1. What is a construction permit?

According to Clauses 17, 18 and 19, Article 3 of the Law on Construction 2014, regulations on construction permits are as follows:

- Construction permit means a legal document granted by a competent state agency to a project owner for construction, repair, renovation or relocation of a work.

- Construction permit with a definite period means a construction permit granted for construction of a work or separate house within a given duration under the plan for implementation of the construction master plan.

- Phased construction permit means a construction permit granted for every part of a work or every work of a project when the construction design of the work or project is not yet completely implemented.

2. Types of construction permits in Vietnam

Construction permits include:

- New construction permit;

- Repair and renovation permit;

- Relocation permit;

- Definite-term construction permit.

(Clause 3, Article 89 of the Law on Construction 2014, amended in 2020)

3. Cases in which construction permit is exempted in Vietnam

Cases in which construction permit is exempted include:

- Works involving state secrets; works constructed under emergency orders;

- Works of projects using public investment funds in which the construction investment is decided by the Prime Minister, heads of central-level agencies of political organizations, People’s Supreme Procuracy, People’s Supreme Court, State Audit Office of Vietnam, Office of the President, the Office of the National Assembly, ministers, heads of ministerial-level agencies, Governmental agencies, central-level agencies of Vietnamese Fatherland Front and of socio-political organizations or chairpersons of People’s Committees at different levels;

- Makeshift construction works as prescribed in Article 131 of the Law on Construction 2014;

- Works undergoing repair or renovation of their interior parts or works undergoing repair or renovation of their external architecture not facing roads in urban centers subject to architectural management requirements of competent state agencies; such repair or renovation does not alter the functions and force-bearing structures of the works, and must be conformable with construction planning approved by competent state agencies and requirements on fire and explosion prevention and fighting, and environmental protection;

- Advertisement works not subject to construction permits as prescribed by the Law on advertisement; passive telecom infrastructure works as prescribed by the Government;

- Construction works located in the territories of two or more provincial-level administrative units, works constructed in lines outside urban areas which conform to construction planning or detailed planning approved by competent state agencies;

- Construction works of which results of appraisal of the construction design following the fundamental design have been notified by specialized construction agencies to meet conditions for approval and which meet requirements for construction permit prescribed by this Law;

- Detached houses with under 07 stories of urban area construction investment projects or housing construction investment projects under detailed planning of 1:500 scale approved by competent state agencies;

- Grade-IV construction works or detached houses with under 07 stories in rural areas without urban planning, function zone construction planning or detailed construction planning on rural residential points approved by competent state agencies;

Grade-IV construction works or detached houses in mountainous areas or islands without urban planning or function zone construction planning, except detached houses built in conservation zones or historical and cultural relic zones;

- Project owners of construction works prescribed in Points b, e, g, h and i of Clause 2, Article 89 of the Law on Construction 2014, except detached houses prescribed in Point i of Clause 2, Article 89 of the Law on Construction 2014, shall send written notices of the time of construction commencement and construction design dossiers to local construction management agencies.

(Clause 2, Article 89 of the Law on Construction 2014, amended in 2020)

Ho Quoc Tuan

>> CLICK HERE TO READ THIS ARTICLE IN VIETNAMESE

121 lượt xem



Related Document
  • Address: 19 Nguyen Gia Thieu, Vo Thi Sau Ward, District 3, Ho Chi Minh City
    Phone: (028) 7302 2286
    E-mail: info@lawnet.vn
Parent company: THU VIEN PHAP LUAT Ltd.
Editorial Director: Mr. Bui Tuong Vu - Tel. 028 3935 2079
P.702A , Centre Point, 106 Nguyen Van Troi, Ward 8, Phu Nhuan District, HCM City;